|

Installing
a diesel fuel tank at a hospital addition challenged an Omaha
company to come up with an innovative approach to the task.
By Greg
Northcutt
When American Backhoe
Co., of Omaha, NE, won the contract to excavate and install
a diesel fuel tank at a new hospital addition in Winnebago,
NE, it faced a job that challenged its typical approach to
this type of work.
The environmental
contracting firm specializes in hazardous-waste removal and
containment, tank installation and removal, and utility installations.
Still, it had never faced a project quite like this. Normally,
installing a fuel tank is a fairly straightforward job for
the company: Put in a sheet pile system to prevent cave-ins.
Dig the pit. Set the tank in place. Then, remove the shielding
and backfill the excavation to finish the project.
In this case, the
job called for installing a 15,000-gallon fiberglass tank
to power backup generators as part of a US Army Corps of Engineers
project to expand a health care facility for the Native American
Tribes of Northeast Nebraska, Northwest Iowa, and Southeast
South Dakota. However, several factors complicated this particular
installation:
- A tight fit. Installing the 8.5-foot-diameter tank, which measured 36
feet long, required a trench shielding system that would
provide and maintain an unobstructed opening at least 46
feet long, 16 feet wide, and 16 feet deep. The required
excavation would leave just 8 feet of clearance between
the edge of the pit and three structuresa retaining
wall on one side and a concrete slab for HVAC equipment
and a utility building on another.
- Nearby utilities. The work also meant protecting a water main. Located 6 feet
deep and parallel to the excavation, it ran between the
edge of the pit and the concrete slab and utility building.
Other adjacent utilities plus railroad tracks and a street
restricted access to the site.
- Structural
concerns. To prevent structural damage to the existing hospital
building while protecting sensitive equipment, such as computers,
imaging devices, and other high-tech hospital systems, no
heavy vibrations could be generated while doing the work.
- Challenging
soil conditions. The soil was C-60 weak clay down to 8 feet.
Also, as it turned out, the water table was just 9 feet
below the ground.
Choosing a Shielding
System
Facing these conditions, Wally Kanne, American Backhoes
project superintendent, considered his options for protecting
workers from cave-ins:
The threat of structural
damage from vibrations during installation eliminated the
use of a sheet piling system, which would have required a
diesel or vibratory hammer to drive the sheets and piles.
Even if this approach had been allowed, it would have required
a site-specific engineering plan stamped by a Nebraska professional
engineer. A beam and plate system would also have required
an engineering plan for this project plus the added cost of
drilling equipment and a crew to install the soldier piles.
Also, both approaches are typically most cost-effective for
shielding projects that involve both longer trenches and longer
duration. However, for this job, the shielding system would
be in place for only three days.
Kanne turned to
Todd Hayes, with United RentalsTrench Safety Division
of Council Bluffs, IA, for advice. The two had worked together
on a variety of trench and pit shoring systems in the past.
Hayes recommended
Efficiency Productions Slide Rail System for this particular
application. His company has rented this system to contractors
for many other successful projects. Also, because United Rentals
stocks the system, it would be readily available.
 |
PHOTO: AMERICAN BACKHOE |
| The second of two liner posts is installed for the second bay of the shielding system. |
Kanne had never
used a slide rail system, but he liked the advantages of this
approach. It not only meets the shielding requirements of
a steel sheeting or beam and plate system, but installation
is easier and faster. It can be installed using onsite equipment
and a smaller crew. The modular system is also more versatile.
It can be easily adapted to fit a variety of excavation sizes
and configurations. As a result, rental and installation costs
of this slide rail system can be as much as half the cost
of a steel sheeting system, Hayes notes.
Like all trench-protective
systems, this slide rail system has an OSHA-required manufacturers
tabulated data sheet of tables, charts, and other information,
which is approved by a registered professional engineer and
used to design and construct the system.
Also, it
was important to work with a distributor, such as United RentalsTrench
Safety, who has experience installing slide rails on many
projects with various applications and who can provide the
equipment within several hours of when we need it, Kanne
adds. We were on a tight schedule and couldnt
afford to wait for equipment from a dealer or manufacturers
hundreds of miles away.
Installation
Procedures
Kanne and his crew installed a three-bay linear slide
rail system, consisting of panels, linear posts, and corner
posts. With two 16-foot bays on either end and one 14-foot
bay in the middle, it measured 46 feet long and 16 feet wide.
Typical excavation
site equipment, a large excavator and a front-end loader,
was used to install the system.
Unlike tongue-and-groove
posts, unique open-face corner posts of this system provide
a margin of error in terms of keeping the system plumb and
level during installation. This design minimizes post and
panel binding when installing the system down to grade, allowing
panels to be inserted easily, even if the system is not truly
square.
Unlike sheet piling,
in which the sheets are driven to the desired depth before
the pit is excavated, slide rails offer a dig-and-push approach
in which the pit is excavated as the system is installed.
After digging a pilot trench several feet deep, the first
8-foot-high panel is placed in the cut and the ends are inserted
into the outer guides of corner or linear posts. Then, one
after another, additional panels and posts are installed and
connected to enclose the perimeter. Once the system is in
the desired location and the posts are perpendicular, the
panels are backfilled on the outside to secure the system
in place.
Then, excavating
and pushing the panels and posts down in 1-foot increments
using an excavator bucket and alternating from one end to
the other, the system is installed to the bottom of the excavation.
When the excavation reaches the 8-foot depth, another panel
is inserted into the interior guide of the posts and the dig-and-push
process continues until the edge of the bottom panel reaches
the desired depth of the excavation. Using either 4- or 8-foot-high
panels, this system can be built to depths of 24 feet or more.
The system is removed
much the same as it is installedin increments. After
backfilling and compacting in a 2- to 4-foot-high lift, the
panels are pulled up and the process is repeated until the
entire pit is backfilled and compacted.
A safety officer
and a Corps of Engineers representative were onsite
overseeing this installation.
A Smooth Process
The panels went in really smooth, Kanne says.
We were able to keep things nice and level and had no
problems with binding.
The Efficiency
ClearSpan tie-back waler system was used so the parallel beam
spreaders could be pulled out for a continuous unobstructed
opening once the entire system was set.
The wide-flange
beams bolt together and pin to the side panels, Kanne
explains. This holds everything together when you remove
the spreaders to get a continuous unobstructed opening after
the system is set up.
Wide-flange beams
were also attached to the bottom of the linear posts to prevent
the posts from toeing in. These beams were abandoned in place,
since the tank installation prevented their removal.
Other slide
rail systems require a welder onsite and a tremendous amount
of time to weld the linear posts to the beams used to prevent
the system from cantilevering, Kanne says. This
Efficiency tie-back design with a C-clamp allows multiple
slide rail bays to be built in both directions while working
within OSHA regulations.
A Wet Surprise
Not long after starting excavation work, the crew hit
groundwater at a depth of 9 feet. This water pushed the weak
clay soils up from under the shoring system and threatened
to undermine the water main and adjacent structures. Three
pumps, running 24 hours a day, were able to remove the water
to prevent buildup, and sand was filled in under the water
main to protect it.
The knife edge
on the bottom of the slide rail system allowed Kanne to push
the panels several feet below the excavation level, creating
a dam to stop water from flowing into the pit. Once the water
was under control, a single pump at the bottom of the excavation
was sufficient to prevent water from accumulating. However,
dealing with the water and related problems threw the project
behind schedule.
The pressure from
this water also affected removal of the panels, which was
done with a crane and excavator. The initial lift was
hard, Kanne says. But, once the hydropressure
was off, the panels slid right out.
Assessing the
Results
With no prior slide rail experience, Kanne was hesitant
to try this approach at first. But the results quickly changed
his view.
I was really
pleased with it, he says. This system installs
a lot faster and much easier than a sheet piling or beam and
plate system. We were able to dig down to grade in just two
days. It would have taken six to 10 days to reach grade with
a beam and plate system. The slide rail system saved us a
lot of time. In fact, using this equipment and working with
good people helped get us back on schedule to complete the
project on time.
Greg Northcutt
writes frequently on construction and business issues.
GEC
- July/August 2005
|