By Larry
Trojak
Excavation-based
utility projects in which rock is knowingly or unknowingly
encountered can be among the most challenging and vexing to
a contractor. Timelines that once seemed real suddenly begin
to slip until deadlines themselves appear in jeopardy. For
one Wisconsin contractor, planning ahead with the purchase
of an excavator-mounted grinding attachment not only helped
keep a project on schedule, it beat the performance of traditional
equipment by a 2:1 margin.
The Town of
Bedrock
In a project for
the Milwaukee (WI) Metropolitan Sewage District, portions
of the city's Lincoln Creek are undergoing reshaping
and deepening to alleviate flooding in the area. The $5.1
million project, dubbed "Lincoln Creek Flood Control
Phase IIUtility Relocation," isat the same
timeaccommodating the removal and widening of a nearby
bridge. According to Doug Stoffel, project manager for excavation
contractor Super Excavators Inc. of Menomonee Falls, WI, the
creek was not much of a formidable challenge; what lay below
it, however, was.
 |
 |
"Lincoln Creek
itself is about 25 feet wide and, at most, about 3 feet deep,"
Stoffel states. "This particular facet of the job involved
relocation of an existing 16-inch water main, a move that
meant we had to lower it an additional 10 feet from its current
depth. The project involved boring under the creek with casings,
so we needed to install a work shaft for the jacking operation.
Ordinarily that would be a run-of-the-mill job. In this case,
however, going to that depth put us in about 22 feet of bedrock."
Getting Down
to Boring Work
To meet the boring
contractors specs, a work shaft measuring 35 ft. long x 10
ft. wide x 37 ft. deep was needed. Of that 37 ft., the top
15 ft. of material was overburden consisting mostly of clay,
but the remaining depth was solid Wisconsin limestone. Once
they were at 37 ft. and had the work shaft dug, using an auger
system, the crew would bore under the creek, recounts Stoffel.
"In an ideal
situation, blasting through that rock would be the logical
approach; in fact, it would be the preferred method for removing
that rock layer. However, the proximity of an existing bridge
and the need to maintain an uninterrupted flow of traffic
removed that option from consideration. In preparation for
this project, we saw what a Genesis Cyclone [a rock and concrete
processor from Genesis Equipment & Manufacturing Inc.
in Superior, Wisconsin] could do and felt that it would be
the ideal tool for this project. We were right on the mark
with our assessment. The attachment, mounted on a Komatsu
PC650 [excavator], went through the rock layer with no difficulty
at all. Had we been forced to use hydraulic hammersthe
traditional tool when blasting is out of the questionwe
would have easily taken twice as long on the project."
The Perfect
Storm
The Cyclone is
a rotary attachment that uses the excavator's existing
hydraulics to provide the rotation of the tool and pin-on
carbide teeth to process even the hardest rock and concrete.
Since its introduction, utility companies and contractors
have found the Cyclone to be a true, viable alternative to
blasting and the use of hammersparticularly in applications
in which vibration or collateral damage is a concern.
"We would
still be out there doing this job with the hammers,"
believes Stoffel. "And in addition to the obvious benefits
we realized in speed and elimination of vibration, there were
other benefits that we hadn't even considered. For example,
the cut is a lot cleaner than anything we would get with either
a blast or a hammer. In the case of a hammer in particular,
because they tend to slip off a rock ledge being processed,
we are mostly left with rough edges in our rock-based digs.
The Cyclone provided a nice, uniform, even cut. And the 100-plus
yards of material we brought up from the creek project were
so uniform in sizeranging in size from three-fourths
of an inch to one and a half inchesthat it looks a lot
like what we call traffic bond.' We stockpiled
the material and will utilize it as fill in washouts and other
projects around our yard. In other cases, it can simply be
used on-site as fill."
Once it wrapped
up the project on the south side of the creek, Super Excavators's
crew moved to the opposite side to make a similar but smaller
cut.
"The second
dig was probably about 6 feet wide by 20 feet long and, again,
the same depth. Once the casing was exposed, we hooked onto
the pipe, brought it up, and reconnected to the existing water
main running from the street.
Additional Work
Ahead
Stoffel says that
with the Cyclone in their arsenal, they feel they will be
better equipped to take on additional projects that in the
past might not have been as well suited to their capabilities.
"Watching
the machine, and in discussions with our superintendent and
our president Jeff Weekly, we definitely find that it will
be a useful tool for us in any number of open-cut scenarios,"
he states. "There are areas around here in which rock
ledges jump up and then, just as quickly, jump back down again.
On other projects in which that has occurred, we've had
to stop, call in a blasting contractor, wait for them to free
up the rock layer, and then proceed. Now we will bring in
the Cyclone, grind the rock out of the way, and continue along."
Larry Trojak,
president of Trojak Communications of Coon Rapids, MN, is
a marketing communications professional who writes extensively
on construction, material handling, demolition, and recycling
issues.
|