Customers of the
Ute Water Conservancy District in Grand Junction, CO, will
be enjoying better-tasting drinking water ahead of schedule,
thanks to an early completion of a tunnel that houses part
of the district's new raw-water transmission pipeline.
Affholder Inc.
of Chesterfield, MO, a subsidiary of Insituform Technologies
(www.insituform.com)
that uses tunneling methods to perform trenchless installations
of new pipelines throughout North America, completed excavation
for the second and final tunnel for the district's raw-water
flow line more than a month ahead of schedule, setting a one-day
tunneling record in the process, according to Brent Duncan,
project engineer for Affholder.
A work crew began
boring the 9,916-ft. Lower Canyon Tunnel on September 7, 2000,
just days after completing the 3,300-ft. Lower Mesa Tunnel
farther up the mountainside. It emerged on the other side
on March 16, 2001, having excavated through an average of
79 ft. of sandstone and siltstone rock a day.
That's a good pace,
remarks Duncan, considering that the rock they were boring
through is more than five times stronger than the concrete
typically used in highway construction.
The crew was also
aided by an exceptionally strong start. On September 14, 2000,
workers excavated through 219 ft. of rock in a single shifta
record for a 10-ft.-diameter tunnel of this kind, according
to the manufacturer of The Robbins Company tunnel boring machine
they were using.
"On that day
we were still near the beginning of the tunnel," recalls
Duncan. "So the turnaround time for the trains carrying
debris from the tunnel was very fast. Everything was working
in our favor."
Good fortune, in
fact, appeared to stay with the project from its very beginning,
notes Duncan. "In no way was this a straightforward job,"
he adds. One of the portals where the project team entered
the mountain, for example, was more than 275 ft. above
ground level, with no passageway leading up to it. Workers,
as a result, had to build a road and a launching area so they
could access the work site and had to run power generators
day and night for electricity.
Because the tunnels
run adjacent Plateau Creek, an ecologically sensitive area
rich in fish and wildlife, the crew needed to take special
precautions while performing drill and blast activities required
to position the tunnel boring machine on the mountainside.
They also had to be sensitive to the handful of people whose
homes are near the tunnel portals.
When both tunnels
were completed, the Ute Water Conservancy District entered
the final phase of its program to construct its new 13.5-mi.
water transmission pipeline.
Affholder installed
13,543 ft. of new 48-in.-diameter steel pipeline in the tunnels.
These pipelines were connected with the nearly 11 mi. of underground
pipe that Barnard Construction, Affholder's joint-venture
partner, installed using open-cut construction.
The pipeline is
used to transport water from a mountain reservoir east of
Grand Junction to a treatment plant near Palisade, CO. After
the water is purified there, it provides drinking water for
the district's 65,000 customers. The pipeline replaced
a deteriorated 24-in.-diameter concrete pipeline that could
no longer meet the district's demands, explains Ralph
Ohm, project manager for the Ute Water Conservancy District.
"In the summer
months, we often exceeded demand for the old line and had
to pump water from the Colorado River," relates Ohm.
"It's cheaper to treat the water from off the top
of the mountain, and it really is better-tasting water."
The new main became
operational two months ahead of the original schedule. Affholder
and Barnard Construction completed their joint-venture contract
$1.6 million under budget.
|