|
By Debbie
Norton
With Lenexa, KS's
prime location at the intersection of Interstate 35, the Interstate
435 loop, and Kansas Highway 10, more than a million motorists
pass through this growing community of 40,000 residents each
day. With the demolition of one high-profile eyesore that
has sat vacant for seven years, the city is looking forward
to its continued growth as a major business center.
 |
| Lenexa,
KS's Levitz furniture store before demolition |
The former Levitz
furniture store at the corner of 93rd Street and Marshall
Drive is now a memory, making way for a new Costco Wholesale
warehouse that will be built in its place. The two-story,
concrete-block store's demolition, as well as the demolition
of 11 houses in the 12-ac. zone to be occupied by Costco,
presented quite a challenge to Kansas City, MO, contractor
DECO Construction Inc.
"Two things
complicated our job," explains Aaron Bradley, project
manger for DECO. "The first was the fact that the drilled
piers that provided the foundation of the building turned
out to extend from 12 to 20 feet into Kansas bedrock. That
is very unusual for a slab-on-grade structure like that. We
were counting on a standard foundation."
The second obstacle
was the presence of asbestos in the flooring of the store
and in all 11 demolished houses. "All of the houses had
varying degrees of asbestos," Bradley says. "Abatement
had to take place by our specialists before any demolition
work could begin, to comply with federal regulations and to
safeguard the public."
Adding to the complexity
of the job was the tight time frame that Costco gave DECO
to reach completion. "There was a big push to get this
done in a relatively short amount of time, including the additional
roadwork we had to do to prepare the site for construction,"
Bradley recalls. The first phase of asbestos abatement started
on June 25, with final work ending on November 1.
DECO's more
than 17 years' experience handling extensive site redevelopment
throughout the Midwest prepared it for this project. Under
the direction of brothers Steve and Greg Short, DECO has grown
in the number of services it provides and territories it serves
to become one of the nation's top demolition contractors.
In addition to residential, commercial, and industrial demolition,
the company also handles asbestos abatement, plant dismantling
and liquidations, excavation, hauling, and salvage. One major
project that launched DECO into its growth pattern is at Whiteman
Air Force Base in Knob Noster, MO. Starting in 1986, DECO
has maintained a full-time operation there.
Demolition Contractor's
New Challenges
 |
 |
 |
| Various
stages of the demolition process |
In addition to
handling the asbestos abatement, the contractor had to properly
dispose of more than 100,000 fluorescent light bulbs and 2,000
light ballasts, which today are categorized as hazardous waste.
Rather than using
a wrecking ball, DECO workers used grapples and shears to
bring down the 169,000-ft.2 building and its foundation.
The company also put to use its new Caterpillar 345 trackhoe
to root out sections of the building. Sophisticated machines
and attachments such as these are typical of the safer and
more efficient equipment being used by today's contractors.
DECO President Steve Short serves on the Board of Directors
of the National Association of Demolition Contractors, which
sees as one of its functions the education of American business
and the public on the professionalism of modern demolition
contractors.
With the cost of
depositing debris in landfills becoming prohibitive, contractors
such as DECO have developed specialized aftermarkets for construction
and demolition waste. On the Costco project, DECO took the
concrete block from the old furniture store and moved a large
amount of it to use as fill on the construction site. Steel
from the building's frame was sold to a scrap yard, where
it is reprocessed for new uses.
With its expertise
in excavation, DECO worked on a 30,000-yd.3 cut-and-fill
in which the soil is cut off one side of the site and moved
over to the other side, put it in place, and compacted. Another
42,000 yd.3 of soil was hauled off to find use
in another construction site. In addition, DECO demolished
all existing asphalt at the site, cutting the area to final
grade for roadway widening and sidewalk construction. Budget
for the demolition project was $834,000, with an additional
$38,000 for work done on new roads and structures.
Soon to rise on
the site, constructed by general contractor Elan Construction
of Calgary, AB, is a Costco Wholesale Company warehouse, one
of 370 worldwide. The average warehouse size is 133,000 ft.2
Debbie Norton
is safety assistant with DECO Companies in Kansas City, MO.
|