In the winter of
1989, construction of the Kressview Springs condominium in
Cambridge, ON, was underway. An 850-ft.-long driveway embankment
was constructed, ranging in height from 7 to 36 ft. and passing
over areas of a peat deposit up to 8 ft. deep. Conditions
of the construction site, situated on the north bank of the
Eramosa River valley, required the embankment to conform to
a steep, contoured landscape; tolerate differential settlements
as great as 2 ft.; and support heavy vehicles during construction.
These requirements
were fulfilled by Presto Products vegetated Geoweb (geocell)
earth retention system. More than 12 years later, the vegetated
geocell system continues to perform as expected. Referred
to as the "flower pot" wall by residents, the open
front cells of each geocell section form horizontal terraces
where vegetation can flourish. The open cells capture rainwater
while controlling groundwater evaporation, creating a natural
environment for vegetation.
The layered geocell
earth retention system meets all structural requirements,
provides construction flexibility, and is aesthetically pleasing
with a completely vegetated face. The system meets site challenges,
even when the subgrade is compressible, unstable soil.
Phase II Slope
Reconstruction
In the summer of
1998, a new geocell earth retention system was installed at
Kressview Springs condominium. The condominium corporation
decided to construct a vegetated retaining wall 280 ft. long
with a maximum height of 30 ft. in front of the buildings
main entrance. This vegetated geocell wall system replaces
a geosynthetic facing on a steep soil-nailed slope in need
of rehabilitation.
"Considering
the successful performance of the existing Geoweb wall system
over the past years, the system was the obvious choice for
the reconstruction work," says Mike Walsh of AGS Canada,
Prestos distributor.
The Original
Geosynthetic System
The existing steep
soil-nailed slope was originally constructed in 1988 prior
to the geocell wall supporting the driveway embankment. The
original 1:2 slope on the river-valley bank was excavated
to a near vertical cut approximately 33 ft. high. The cut
was made so the slope had three terraces 6.5 ft. wide to provide
better visual appeal to the condominiums residents.
The slope material
comprised dense glacial till, ranging from silty clay to silty
fine sand. Lenses of more clayey soils were found throughout.
These lenses acted as horizontal dams causing several water
tables to flow to the face, thus providing a source of water
for icing in the highly frost-susceptible silty soil.
"A soil-nailed
system with a geosynthetic facing was chosen to permit drainage
throughout the face of the structure while allowing for potential
soil movement," explains Walsh.
The system was
constructed by first drilling and grouting 600 1-in.-diameter
Dywidag soil nails into the face of the slope. The soil nails
ranged in length up to 39 ft. and were installed in a series
of horizontal rows to facilitate connection between the nails.
The geosynthetic fascia was then applied and anchored using
the soil nails.
Installation
of the New Geocell Wall System
The reconstruction
utilized the existing soil nails but replaced the geosynthetic
fascia with the geocell. The geocell wall system, at 30 ft.
high, permitted drainage throughout the face of the structure
while accommodating potential soil movement.
"The rehabilitation
of the steep slope began with removing the geosynthetic fascia
and all vegetation that had grown over the past 10 years,
leaving a grid work of exposed soil nails," describes
Walsh.
The contractor,
Cambridge Landscaping Inc., prepared a level pad constructed
from granular B, Type II, 1 ft. thick and compacted to 95%
minimum Standard Proctor Dry Density (SPDD).
Next, the geocell
sections with a black textured fascia and internal perforated
cells were placed and expanded on the granular pad.
"The cell-wall
perforations create good frictional interlock with the aggregate
and allow lateral drainage through the system. Drainage is
especially important given the seepage of groundwater at various
elevations behind the wall," explains Walsh.
Each 8-ft.-wide
x 2-ft.-long x 8-in.-deep geocell section was expanded and
held open with stretcher bars. Adjacent sections were pneumatically
stapled together to complete a wall course.
Each course was
checked and adjusted to achieve proper elevation, setback,
and alignment. With the exception of the outer cells, the
course was then overfilled with granular B material and compacted
with hand-operated equipment. Once compacted to 95% SPDD,
excess granular was raked away and the next course was installed.
The outer row of cells was filled with topsoil to allow vegetation
growth. This procedure was continued until the full wall height
was achieved. Throughout the construction, geocell sections
were anchored at soil nail locations and elevations.
The geocell sections
were attached to the soil nails using a polyester geogrid,
galvanized steel pipe, and a special soil-nail head attachment.
This process was achieved by first installing the soil-nail
heads to the soil nails, then using the heads to support and
hold the galvanized steel pipe in place. The polyester geogrid
was wrapped around the steel pipe and placed over the filled
geocell sections at the required elevations. Geocell sections
were then placed over the grid. With the grid taut, the geocell
sections were infilled, and the infill was compacted at the
required elevations.
Construction
Challenges
The finished wall
with only front access forced the contractor to resort to
a creative means of placing infill material within the higher
wall courses.
"The lower
sections of Geoweb were filled with a typical front-end loader,"
recalls John Verhoeven of Cambridge Landscaping. "As
the wall height increased, a Loadall with telescoping boom
was used to fill the midsections. When the height was beyond
the reach of the telescoping boom, a 25-ton crane was brought
in."
The crane lifted
a large bottom-dump concrete bucket filled with granular infill
material. The laborers, receiving the bucket at the top of
the wall, dumped the granular into the geocell sections.
The owners chose
not to use conventional hydroseeding but accepted the contractors
recommendation to place individual plants in each of the front
cells. The selected ground cover will spread and eventually
cover the entire face of the geocell wall. The terrace areas
were subsequently planted with a variety of small shrubs.
The vegetation
has developed as expected and is gradually transforming this
geocell wall into a mass of vegetated life. The owners of
the condominium are quite pleased with their new view and
look forward to its seasonally changing appearance in the
future.
"While hydroseeding
provides initial ground cover, the grass grows dormant and
results in a bare appearance," concludes Verhoeven. "That
is why we selected semi-evergreen that ensured continued and
healthy plant growth."
Completed Project
Scope
In total, 5,000
ft._ of wall face was reconstructed in three wall lifts varying
in height from 6 to 30 ft. More than 1,000 geocell wall sections
and 12 rolls of geogrid were utilized for the wall structure.
|