| |
Imagine coming to work
one day and finding its your job to come up with more space
and more dirtwithout breaking the bank. Thats what happened
to the staff at the Olinda Alpha Landfill (OAL), a Class III Sanitary
Landfill located in Orange County, CA, adjacent to the city of Brea.
OAL, situated on 562
ac. of county-owned property, is operated by the countys Integrated
Waste Management Department (IWMD). It is the fourth-largest landfill
in the state of California with a total annual disposal (1999) of
1.9 million tons. The landfills daily maximum permitted disposal
capacity is 8,000 tons, and it receives approximately 6,300 tpd
of waste. The ultimate site capacity is 123.1 million yd.3
OAL was originally permitted
as two waste disposal facilities in adjacent canyons, Olinda and
Olinda Alpha, that were divided by a central ridge. Disposal operations
started in Olinda Canyon in 1960 and proceeded into Olinda Alpha
Canyon in 1981. The portion of the canyon to receive the initial
refuse was prepared by clearing and grubbing the native vegetation.
Excavation was conducted to obtain the necessary cover material,
provide a level deck to conduct unloading operations, and construct
the necessary internal roads to access the unloading area. As operations
progressed, the canyon was filled generally from front to back,
rising in elevation.
In 1987, the Orange County
Board of Supervisors initiated the North Orange County Landfill
and Alternative Technologies Study to identify new sites and/or
expand existing landfill sites to provide replacement solid waste
disposal capacity in the county. The vertical expansion of OAL was
identified as a preferred disposal option. A master plan and various
permit documents were subsequently prepared to obtain regulatory
approval of the vertical expansion. Approval was granted in 1996
after rigorous environmental review.
The master plan defined
a phased approach to the expansion that allowed IWMD to maintain
operations during the construction stages of the landfills
expansion. What is unique about OAL is how the vertical expansion
of the landfill was accomplished. First, the location of the two
landfills side by side lent itself to the strategy of combining
the canyons. Second, an innovative engineering design was created,
providing an alternative solution that fulfilled the prescriptive
requirements of federal Subtitle D regulations. The vertical expansion
at OAL combined the two existing waste management units in Olinda
Canyon and Olinda Alpha Canyon, respectively, for the purpose of
excavating the central ridge separating the two canyonsan
operation displacing 7 million yd.3for a total
combined airspace capacity of approximately 123.1 million yd.3
The master planning exercise
also identified a shortfall in available soil for cover on-site,
determining that it was sufficient only through 2003. Thereafter,
if IWMD were to continue in its accustomed mode of operations, it
would have to import soil at a cost of $7.50/ton. At this rate,
the added cost would amount to $750,000 per year, or in excess of
$5 million through 2013.
In response to OALs
soil shortage, site engineering staff devised a more efficient and
less costly approach to developing the landfill that revised the
projected soil shortfall to the year 2009. Strategies implemented
to defer the projected soil shortfall included increased use of
alternative daily cover (processed greenwaste), revised fill phases
to minimize the number of interim fill slopes requiring large quantities
of soil, and use of existing access roads.
Even as it became apparent
that these strategies would achieve the 2009 target, staff continued
to look for ways to extend the landfills life still further
into the future, and to this end, OAL brought Caterpillars
Computer Aided Earthmoving System (CAES) onto the site to establish
and maintain a uniform deck from which more accurate measurements
could be made.
In October 2001, a global
positioning system (GPS) was installed, and trial operations began
using the CAES to provide efficient refuse grading and compaction.
The system includes an engineering office base station comprising
a surveyed monument, GPS receiver, radio, and computer with CAES
software; heavy-equipment machinery consisting of three tractors
and one compactor, each equipped with a GPS receiver, radio, and
display monitor; and computer hardware and software to assist the
design engineer in the preparation of a 3D grading plan for the
site. Initial data were converted from existing site-planning AutoCAD
files and fed into Caterpillars system. The plan is then converted
into a CAES file and sent via radio signal into each machine. An
onboard monitor shows plan and cross-section views with color-coded
existing and proposed grades, and a color-coded plan view allows
the operator to see the existing ground as fill, grade, or cut.
These displays let the operator visually check the screen for plan
conformance without the requirement for other grade controls in
the field. The machine data are sent back to the CAES computer via
radio and can be downloaded as point files to generate a topographic
of the finished fill grade. The project has demonstrated the systems
benefits in achieving precision grade control, a reduction in soil
cover requirements, improved compaction, safer operating practices,
adherence to regulatory-driven grade requirements, and the preservation
of airspace.
Dave Lowry, OALs
general manager, has become a thoroughgoing fan of the CAES system.
"Were able to save seven- to eight-tenths of a foot over
the entire working face," he notes. "Thats more
than 300 yards of dirt a day." There are many more savings,
although theyre not quite so obvious. "A lot of it is
in avoided maintenancelow areas and erosion repair. Just the
ability to install correct flow lines is a real plus to the operation."
Excavation of the central
ridge began in 1998 and was completed in October 2000. By agreement
between the county and the City of Brea, its closest neighbor, OAL
is scheduled to close in 2013; however, at the present fill rate
and using best management practices, it is estimated that the active
life could be extended to 2017 without additional major construction;
2021 with additional construction.
John Trotti is the
editor of Grading & Excavation Contractor magazine.
|

|
|
The Computer Aided
Earthmoving System (CAES) integrates operations, planning,
and design, and it offers a means for engineers and managers
to show equipment operators exactly what they are doing in
relation to the plan. The result is better use of equipment
resources, higher production, and lower cost. CAES puts a
color computer site plan of the project in front of each equipment
operator whose machine is equipped with the system. The real-time
display is color coded, showing how much material must be
cut or filled and the location of the machine in relation
to the site plan. Operators can view up-to-the-minute plans
onboard their machines, and they can view current topography
and cross-sections, which CAES updates in real time as the
surface is altered. CAES eliminates the need for placing the
hundreds of survey flags that define elevation, grade, slope,
and material type. The system also eliminates problems with
low visibility caused by darkness or inclement weather, because
operators are not dependent on sighting flags or other landmarks.
The CAES system is designed to work with many different types
of equipment, both Cat and competitive, and in several different
applications. Currently systems are available for front shovels
(both hydraulic and cable), wheel loaders, track-type tractors,
scrapers, motor graders, and compactors. The display for each
type of machine is slightly different, but only the onboard
software differs between machines. The system can direct operators
in defining bench elevations in grade and slope in earthmoving
projects, as well as compaction and coverage in earthworks
and landfill applications.
Whats
Behind CAES
 |
CAES uses onboard
computers, software, GPS, and data radios and receivers to
replace conventional surveying. The system accepts plans generated
with conventional computer-aided-design software. Caterpillars
Mining and Earthmoving Technology Systems (METS) software,
called METSmanager, provides a seamless interface for translating
plans into CAES format. Using a high-speed radio system developed
jointly by Trimble and Caterpillar, METSmanager transmits
the information to the appropriate CAES-equipped machine.
The information is in the form of a two-dimensional digital
terrain model. As the machine works, terrain updates, using
GPS technology, are collected and transmitted back to the
office where METSmanager feeds the data to another program,
CAESoffice. CAESoffice can show several machines working at
the same timeon a display similar to those seen in the
machines. The software also combines terrain updates from
all machines working in the field to maintain a single, up-to-date
model of the site. Such data can be exported to the original
planning software when additional design work or plan changes
are needed. CAESoffice also provides immediate, accurate production
calculations. No error-prone, in-field estimates are required.
Instead, supervisors can make operating decisions based on
accurate, up-to-the-minute information. CAES offers a cost-effective,
information-based means to improve operating efficiencies
by delivering the right material to the right place at the
right time. Several commercial systems are now operating in
North America, and each has quickly proven to be cost effective.
At present, CAES
is jointly marketed by Caterpillar and Trimble, who provide
end-user and original-equipment-manufacturer solutions for
diverse applications including surveying, mapping/geographical
information systems, agriculture, mining, military, commercial
aviation, automotive, vehicle tracking, and timing.
|
|
|