|
A recent challenge that management at San Jose, CAbased
Calpine Corp. faced when it needed to retrofit a natural gasfired
cogeneration plant in the Houston, TX, area was a familiar
one: adhere to increasingly stringent environmental standards
in the most cost-effective manner. Unique aspects of converting
the first of three turbines at the 457-MW combined-cycle cogeneration
Texas City power plant, however, were the local environmental
standardsand an available technology for drastically
reducing both NOx and carbon dioxide emissions that minimally
impacted operations, not to mention the facilitys economic
viability.
 |
Calpine had to reduce these emissions at the Texas City plant,
which began operation in 1987 and produces steam for an adjacent
Dow Chemical facility, in the wake of the Houston-Galveston
areas dubious capture of the title Smog Capital
of the US during the past few years. NOx emissions,
in particular, contribute to the development of smogformation
of environmentally harmful ground-level ozone when NOx combines
with volatile organic compounds, such as gasoline vapors,
and the pollutants get trapped near ground level by a combination
of stagnant air and sunlight. The Houston-Galveston-Brazoria
areahome to the nations largest concentration
of chemical processing plantsis designated a non-attainment
area, as it currently does not meet 1990 Clean Air Act
standards for ozone, compelling the Texas Commission on Environmental
Quality (TCEQ) to submit a plan for attainment of the federal
one-hour ozone standard by 2007. In addition, the area must
attain a more stringent federal eight-hour standard with further
NOx reductions between 2010 and 2013.
Patrick Blanchard, director of safety, health, and environment
for Calpines Electric Reliability Council of Texas (ERCOT),
acknowledges that the TCEQs as-yet-undetermined strategy
for adherence to the EPAs more stringent eight-hour
ozone standard added a complication to the plants retrofit.
Rather than go back and reinvent the wheel, we anticipate
that they will be required to further limit the amount of
allowances that are allocated to facilities, he says.
Were still a little ways out from being able to
look into our crystal ball so we can see what our future allocation
rights will be.
Operations, such as the Texas City power plant, are allocated
allowances for emission of NOx based on the area-attainment
plan. (A ton of NOx equals one NOx allowance.) These operations
can purchase additional allowances, or roll over or sell unused
allowances on the open market at the end of a year, depending
on the chosen strategy for managing the problem.
According to Ron Anselmo, P.E., a commercial manager for
ERCOT, the market forces at play made purchasing credits not
viable from a business standpoint. It would even be possible
to purchase a stream of allowances allowing the
emission of NOx in perpetuity, but this carried an unacceptably
high cost of $40,000 per ton. A much better solution would
be reducing NOx emissions. There was more than one way to
achieve this, however.
The Choice of Technology
Anselmo notes that two technologies were available to reduce
the NOx to an acceptable level. A proven technology is selective
catalytic reduction (SCR), which involves the injection of
ammonia into a plants exhaust gas. In the presence of
a catalyst, the ammonia reacts with the gas to produce environmentally
harmless nitrogen and water vapor. The other available technology
was dry low NOx (DLN), which pre-mixes the plant fuel with
air in a separate chamber prior to ignition, allowing for
a lower burning temperatureproducing less NOx.
SCR is a proven technology with which Calpine is familiar.
DLN is a technology with which management was familiar enough;
however, its superior cost-effectiveness began to emerge as
Calpine began to compare the alternatives.
Anselmo notes that it quickly became clear that the SCR option
would be considerably more complicated than the DLN alternative.
Characteristic of capital planning, initial cost wasnt
the only issue. The biggest complications were site space
restrictions and construction time. For one thing, the design
of the existing heat recovery steam generators (HRSGs) wouldnt
allow for retrofitting with SCR equipment; entirely new HRSGs
would have to be installed. While this upgrade would increase
the plant output, it would further restrict the already limited
floor space in the plant.
For the HRSGs, we had to look at buying new equipment;
you had to go out and construct that equipment, and youve
got to have more space for that equipment, Anselmo says.
One thing we dont have is a lot of space on the
property. With our timeline, we thought that with HRSG we
could meet the timeline but wed probably have more risk
if we had a construction problem.
The downsides we saw with HRSG were primarily spaceits
less cost compared to the DLN technologyand construction
time. The biggest drivers were space and construction time.
If we had done the HRSG project, we could have increased the
capacity of the plant, but our main goal was to fix the environmental
problem.
Despite the fact that it requires a conversion of existing
turbines, DLN technology carried a few concerns, too. For
DLN, the downside was that we didnt know if wed
have the flexibility that wed have with the HRSG,
he says. We know how the turbines run now, but we didnt
know how theyd run with the LEC system.
But a huge factor in Calpines decision to go with DLN
was the experience its wholly owned Power Systems Mfg. LLC
(PSM) subsidiary has with the technology. PSM engineers not
only gas turbines but also military jet engines using an ISO
9001:2000qualified design process.
A couple of years earlier, PSM had installed its patented
low-emissions LEC-III combustion system at Dows Oyster
Creek plant in Freeport, TX, and achieved a baseline 4.75-ppm
NOx versus a required 5.0 ppma 62% reduction in addition
to a 100% carbon dioxide reduction.
I think, at the end of the day, PSM has proven to be
a huge resource for Calpine, says Anselmo. Those
guys definitely have the competence to build the hardware.
They build airplane turbines, and we all know that theyre
very efficient and very reliable. That gave us a lot of confidence
internally.
At Texas City, PSM installed its LEC-III system in a 501D5
combustion turbine generator designed by Siemens Westinghouse
and manufactured by Mitsubishi. PSMs Vice President
of Commercial Operations Pat Conroy notes that the project
team was entering new territory on this project in one respect.
That was our first 501D5, he says. The D5
has a different envelope from the GE 7A model we had retrofitted
before, a different pressure boundary, and we had to make
changes to that boundary and replace the pressure combustor
case, and make a couple of other pressure components in order
to accommodate our particular hardware. All in all, when Calpine
and the Texas City folks evaluated the cost, it was still
more cost-effective to put in a DLN system like the LEC-III
than to go with an SCR. It was estimated that the installed
cost and operation of the DLN would save Calpine $36 million
versus an SCR system.
Another plus in using DLN technology was that Calpine was
able to reduce carbon dioxide emissions to single digits.
Achieving reductions in both NOx and carbon dioxide can be
an engineering challenge, however.
You have to have sufficient time with the carbon monoxide
at a high enough temperature so that it will oxidize the carbon
dioxide, says Conroy. At the same time, this temperature
cant be so high as to promote excessive NOx formation.
The engineering trick is that you can have different zones
in the combustor to where if you havent mixed your fuel
and air properly, you might have a streak, a pathway through
that combustion system that may generate a lot of NOx. When
you average that out in the exhaust, instead of having 5 parts
per million of NOx, you might have 15 parts per million. At
the same time in the same combustor, you could have a cold
streak, where youre letting a lot of unreacted carbon
monoxide escape. So you could have the worst of both worlds
if it werent devised, installed, and tuned properly.
Its engineering and attention to detail that has allowed
these premix systems to evolve from 25 parts per million of
NOx, and 20, 30, and 40 parts per million of carbon monoxide
10 years ago down to what we now have in service.
Down to Business
The existing plant consisted of the three 501D5 combustion
turbine generators (CTGs), three HRSGs, a condensing/extraction
141-MW Hitachi steam turbine generator (STG), a mechanical
draft cooling tower, and other ancillary equipment. The facility
interconnects to the ERCOT grid via 138-kV transmission lines.
The facilitys CTGs were originally equipped with a steam-injection
combustion system designed to maintain NOx emissions at 42
ppm when firing natural gas at base load and injecting 870,000
pounds per hour of steam into the CTGs. In order for the facility
to achieve the required 80% NOx emissions reduction, it would
have to achieve less than 9 ppm emissions.
PSM provided all of the hot section (fuel injection)
and steam conversion hardware, as well as site engineers for
technical direction and tuning/commissioning. The Texas City
facility provided the overall construction management, including
millwright support, and onsite control technicians and electricians
to support the installation of the controls equipment for
the outage. The facility also managed standard wiring, conduit
and related electrical hardware for the controls installation,
and the insulation for the engine cases and piping.
Conroy acknowledges some of the challenges that resulted
from retrofitting the 501D5 compared with the General Electric
turbines with which it had considerable previous experience
retrofitting. Converting a turbine like the 501D5 requires
substantially more work replacing different components, adding
fuel manifolds, fuel management skidsgenerally speaking,
adding more horsepower and modernizing it. There are a lot
of site specifics. There are also a lot of model-specific
differences.
There was a good amount of detail and precise preparation
and engineering, Conroy adds. That occupied a
considerable amount of time by our folks, plus the folks on
the site, because all of these power plants are always one-of-a-kind
installationstheyre always part of a larger integrated
system. We worked closely with the plant staff to make sure
that the physical stuff was all right, and then we did have
to upgrade the control system because the control system on
the machine was probably 20 years old. That had to be upgraded
substantially in order to get the additional processing power
thats needed to manage a DLN-type combustion system;
that combustion system is integrated into the control algorithms
that control the gas turbines. Its not a matter of digital
pulses or voltage; its much more complex than that because
youve got to start the machine up, youve got to
transition between modes, so it was a substantial amount of
work.
Fine-Tuning Integration
The control manufacturer, Emerson, which is a spin-off
of Westinghouse, was the original control supplier,
notes Conroy. Theyre pretty familiar with those
old-style Westinghouse controllers, so that helped. We provided
the logic to them. Also, the plant people provided the required
interactions for the control system between whats called
the balance of the plant, the rest of the power system, and
the gas turbine control, so that was at least a three-way
interaction. And then youve got to physically install
it; youve got a lot of wires that have to be disconnected
and reconnected, and the ones that have been in there for
20 years, youve got to make sure theyre not too
corroded. All of this had to be done on a restricted space
environment.
However, in Conroys previous experience, as well as
in the case of Texas City, the LEC technology has also had
much less impact on the plants controls once its
in operation versus SCR. Its pretty transparent
to the operators, he says. Thats one of
the reasons why people like our system over the SCR. When
you go with SCR, youre putting a chemical processing
unit on the back of that machine, so you have to handle ammonia,
and youve got a vaporization skid, blowers, hardware
that you not only have to buy, but youve got to tune,
test, et cetera. What we do to the gas turbine doesnt
add much to the part count, doesnt make the operators
control of the control panel any different. It doesnt
substantially increase the inspection and maintenance burden
on the crew, either.
An Industry First
Retrofit work on the first turbine began March 3, 2005, and
its first firing was April 16, 2005. The plant ran at partial
capacity during this time, which coincided with its off-peak
season. In 2006, Calpine anticipates that retrofitting of
the remaining two turbines will be complete, providing plenty
of margin for meeting the 2007 requirements. By the conclusion
of the project, PSM and Calpine had achieved an industry first
by reducing NOx emissions from a natural gasfired 501D5
turbine while reducing carbon dioxide emissions. The LEC technology
lowered NOx emissions at normal operation at baseload beyond
expectations, to less than 8 ppm. This more than met the 80%
NOx reduction requirement.
An additional benefit resulting from the retrofit is water
savings. The old system lost about 150 gpm of demineralized
water per turbine up the exhaust stack at base load. Today,
with the PSM LEC-III system in place, TCC is no longer losing
that quantity of demineralized water to the atmosphere.
While DLN was the right solution for this project, Conroy
points out that both DLN and SCR have respective advantages.
In fact, Conroy maintains that SCR generally provides greater
reductions in NOx and suits permits in areas with greater
NOx emission restrictions than does DLN. Given the limitations
of both of those types of technologies, youre not going
to see one replace the other anytime soon, he says.
SCR can get the tailpipe NOx coming out of the back
end of a system lower than the DLN can. Youre talking
about 3 parts per million in our best systems, and you see
SCRs at 2 [parts per million]; youre wringing the last
bit of NOx out of the system. The costs of doing that tend
to escalate, though.
One of the things our customers really like to not
have to deal with is the operation and maintenance of the
SCR. Also, the fact that the type of SCR were talking
about requires you to have a steam recovery boiler that needs
gas in the 400 to 600--degree-Fahrenheit range, whereas the
exhaust gas out of the turbine is more like 900 to 1,000 degrees
Fahrenheit. You need to cool that gas off, and it takes a
heat recovery steam generator that takes that heat and converts
it into useful energy in the form of steam, or you can put
in huge air dilution blowers that force ambient air into the
exhaust steam to lower the temperature. Youre talking
hundreds of horsepower just to blow this air into the exhaust
to lower the temperature.
In the case of Texas City, though, DLN was the clear choice
from both an environmental and economic standpoint.
It boiled down to a viable economic decision that would
be cost-effective internally but also satisfy the NOx requirements
going forward, such that it wouldnt interrupt our business
and keep our steam hosts and our market provider whole,
Blanchard concludes.
Communications specialist DON TALEND
resides in West Dundie, IL.
DE - January/February
2006
|