|
Warm weather and multiple entertainment venues draw more
events and visitors each year, requiring the Orange County
Convention Center in Orlando, FL, to constantly expand. The
latest Phase-V expansion project consists of 2.8 million square
feet of exhibit and meeting space, making it the largest public
project in Orange County history. Combined with the other
four phases, the total complex is now the second largest convention
center in the US. To make sure that the new addition had a
reliable supply of standby power for lighting, security, and
life-safety systems, the general contractor, Hunt Construction
Group, turned to Cummins Southeastern Power for an unconventional
solution.
The Phase-V building is an entirely separate structure with
its own standby power system. Other phases of the sprawling
convention center have their own standby power systems, too,
but this newest standby power system is unconventional in
several ways, according to Mike Sincavage, electrical manager
for Hunt Construction. The most unusual aspect is that the
standby power system is located in a separate building approximately
.5 mile from the Phase-V building. The generators are connected
by a high-voltage, underground power line (15 kV) to minimize
line losses; and communication with the 72 automatic transfer
switches is carried out over a fiber-optic cable system. The
power systems PowerCommand Digital Master Control also
communicates with the facilitys building management
system (BMS) for various operations and maintenance functions.
Backup for Lighting, Life-Safety Systems
The standby power system in the Phase-V expansion consists
of four 1,500-kW PowerCommand diesel generator sets from Cummins
Power Generation, along with associated controls, switchgear,
and automatic transfer switches. The 6-MW standby power system
is designed to provide backup power for all the lighting in
the complex, the ventilation fans, refrigeration in the four
food-service courts, elevators, and security systems in the
event of a utility power failure. This would allow visitors
to safely exit the building from the main show floor and upper
galleries; maintain basic security systems; and prevent food
spoilage in the event of a prolonged outage.
 |
| The remote power building houses four 1500-kW standby generator sets from Cummins Power Generation. |
 |
| Approximately 6 MW of standby power is available within
8 seconds of a utility power failure. |
The new standby power system is one of several layers of
power redundancy built into the new Phase-V facility. With
11 separate feeds from the Orlando Utility Commission for
a total connected load of 36 MW, it would seem that the complex
is well protected from utility outages. But, according to
Sincavage, Orlando is the lightning capital of North
America, and momentary outages are common. Whats
more, hurricanes and tropical storms are also common and capable
of widespread devastation that affects multiple utilities,
substations, and power lines. The standby power system was
required to ensure the utmost in power reliability and the
safety of tens of thousands of convention visitors.
2004s Hurricane Charley Tests System
The building was not hosting a show when the eye of
Hurricane Charley passed directly over Orlando and knocked
out a significant amount of power in the area. Although some
buildings in the convention complex did not lose power, the
Phase-V complex did, and the new standby power system came
on and operated as designed for several hours, says
Brian Kennedy, assistant HVAC supervisor of the Orange County
Convention Center. Anytime the automatic transfer switches
sense a power loss from any of the 11 utility feeds, they
send a signal to start the generators.
When a power outage occurs, all four 1,500-kW generators
start and come up to operating speed in about eight seconds.
The first generator to reach speed and proper frequency closes
with the main bus. If one or two generators are sufficient
to carry the emergency load, the other two generators shut
down automatically and return to a standby mode. When normal
utility power is restored, a signal from the automatic transfer
switches sends the generators into a cool-down
mode before shutting them down. With 10,000 gallons of diesel
fuel on hand, there is enough fuel to power all four generators
for 24 hours. With the current level of standby power demand
at only about 2 MW, there would be sufficient fuel for about
three days, says Kennedy.
The whole standby system is automatic, Kennedy
continues. Plus, it is designed to fail-onmeaning
that even if the fiber-optic communication network fails,
the generators will start and be available for power.
Oversized for Reliability, Growth
With a current emergency load on the generators of only about
2 MW, the 6-MW standby system is significantly oversized.
Citing that as a good thing, Kennedy says that
the larger system provides enhanced reliability in the event
that one of the four generators fails to start, or one of
the units is down for scheduled maintenance. The larger system
also provides capacity for growth as the facility expands
or as other critical loads are identified. The off-site power
building was designed to house an additional 6 MW of generation
(for a total of 12 MW) should that be necessary for future
growth.
According to Sincavage, the four 1,500-kW generators provided
more generating capacity in a smaller footprint than a previous
design involving six 1,000-kW generators. Not only did
the Cummins generators provide more capacity in a smaller
footprint, but we liked the fact that the generators, transfer
switches, and digital controls were all pre-integrated and
came from a single source, he says. With the PowerCommand
digital controls built right into the generators, it simplified
a number of control and communications issues.
Building Management
System Integration
A major advantage of the PowerCommand digital control system
is its ability to interface with building automation and management
systems. This provides system operators with a continual,
functional remote view of the standby power system and how
it relates to the rest of the systems in the building complex.
The standby power system is tied directly into our
Johnson Controls BMS, explains Kennedy. We have
it set up so that whenever the generators start, the BMS issues
an alarm condition that tells us that the generators are running
and available for power. It also provides us with information
on coolant temperatures, fuel levels, and other diagnostics
without having to go to the power building. All this can be
supervised from our central energy control center across the
street, which is manned 24/7.
The BMS can also control the priority of certain loads and
decide which loads need to be shed if there is not enough
standby generating capacity available. The BMS can analyze
how much capacity is available and shut down some ventilation
fans or refrigeration if needed, says Sincavage. The
BMS is also helpful from a maintenance standpoint. System
diagnostics can be performed and historic reports generated,
in addition to other maintenance procedures that enhance reliability.
To further enhance reliability, Kennedy says they have a
two-year maintenance agreement with the local Cummins distributor
to perform all required maintenance on the standby power system.
Experience has shown that regular maintenance is the most
important factor in power-system reliability.
The Orange County Convention Center will no doubt continue
to grow as a leading convention destination for organizations
and industries all over the world. The thousands that will
attend events at the new Phase-V facility can take comfort
in the knowledge that an unconventional standby
power system is adding to the certainty that theyll
have a great convention experience.
BOB SHELDON is public relations director for Creative
Communications Consultants, in Minneapolis, MN.
DE - November/December
2005
|