|
Its a complaint heard in as many as 90% of DE projects,
according to one study; namely, the sometimes ridiculously
tough, seemingly arbitrary, prohibitively expensive, and overly
finicky requirements to be met for parallel grid interconnection.
After years of DE firms simply enduring the situation, recent
developments suggest that matters may be moving in the right
direction. Just this May, the Federal Energy Regulatory Commission
(FERC) issued its new Rule 2006, which should prove a major
step forward in defining, streamlining, and standardizing
small generator interconnection procedures (SGIP) and standardizing
small generator interconnection agreements (SGIA). Issued
mid-May and becoming effective in August 2005, the rule directs
public utilities that do interstate electrical transmission
to amend the open-access transmission tariffs (OATT) and offer
non-discriminatory, standardized interconnection service.
Observing that, historically, Public utilities had
the incentive to engage in, and had engaged in, unduly discriminatory
transmission practices, FERCs standard will perhaps
correct that situation, starting fairly soon. The hope and
goal is to see interconnect barriers lowered to the practical
minimal-point needed to assure system safety and reliability.
(For Rule 2006 summary provisions, see sidebar.)
Why, you may wonder, has interconnection required a federal
ruling? Historically, although the Public Utility Regulatory
Policies Act of 1978 (PURPA) was aimed at opening the nations
grids to customer-owned interconnected generation, the reality
has proven tougher than was envisioned. Electric utilitieshaving
almost no incentive to make the process easy, and several
reasons to thwart ithave typically forced developers
to run a gauntlet of expenses and vexing hurdles. Over the
years, such anticompetitive conduct has been investigated
academically a few times, perhaps most notably by the National
Renewable Energy Laboratory (NREL) in 2000, under the DOE.
This resulted in a lengthy report, Case Studies of Interconnection
Barriers and their Impact on Distributed Power Projects. NREL
completely confirmed the scope and severity of DG developers
difficulties. More positively, the report also presented a
10-point action plan for correction. Over the ensuing years
all 10 points have been incorporated, to varying degrees,
in several new industry standards and model interconnection
agreements.
Greatly complicating the reparative challenge is the fact
that FERC oversight and rulemaking overlap and compete with
that of 50 state regulatory bodies. FERC governs interstate
electrical commerce, of course, while each state regulates
business within its own borders. Scores of utilities and transmission
organizations are governed both ways.
The difficulties notwithstandingand with growing awareness
of the nations need for more diversified and renewable
power generationthe DE industry has been witnessing
a steady succession of important breakthroughs.
Examples include:
- Beginning in 1999, aggressively favorable state regulatory
commissions in New York, Texas, California, and Ohio have
issued rulings to lower interconnection barriers and standby
rate charges.
- October 2001: FERC initiated its first major distributed-generation
rulemaking, which culminated in 2003 with Rule 2003(c) standardizing
the interconnection procedures and business terms for large
generators, i.e, those yielding 20-plus megawatts.
Like the new Rule 2006 for small generators, the earlier
prototype applies to the approximately 176 regulated utilities
and transmission providers engaged in interstate wholesale
transmission and distribution.
- February 2002: The National Association of Regulatory
Utility Commissioners (NARUC), seeking to foster state-level
electrical tariffs and policies on DE-grid interconnections,
passed a resolution supporting the development of two model
DE interconnection procedures and business agreements. By
October 2003, NARUC had issued its Model Interconnection
Procedures and Agreement for Small Distributed Generation
Resources.
- 20022005: In a survey of initiatives underway in
the 50 states conducted by the National Regulatory Research
Institute (NRRI), five statesDelaware, Florida, Idaho,
New Hampshire, and Virginiahave now approved DG-favorable
documents, while a half-dozen othersArizona, Michigan,
Minnesota, Missouri, New Mexico, and Wisconsinare
entertaining drafts, proposals, discussion papers, or interim
procedures. Sixteen member-states of the Southern States
Energy Board have endorsed Texass model DG interconnection
standard as a prelude to regulatory ratification.
- January 2004: The New York State Public Service Commission
ordered a waiver of standby charges for new DG resources
of less than 1 MW meeting certain cogeneration efficiencies.
- July 2004: The IEEE issued its critically important Standard
for Interconnecting Distributed Resources with Electric
Power Systems, designated IEEE 1547. This addresses
the performance, operation, testing, product quality, and
safety of interconnection of hardware and software for DGwith
additional subset standards and related issues still being
ironed-out to cover DG control, communication, interoperability,
design, engineering, installation, and certification, according
to IEEEs Web site. Based on input from several hundred
organizations, the 1547 series should completely encompass
all technical and engineering standardization related to
DG, greatly enhancing progress and efficiency.
- Feb 2005: The California Energy Commission completed a
revision of its five-year-old Rule 21 interconnection procedures,
with the effect of boosting DG-favorable treatment even
further.
None of this represents what might be considered perfect,
universal standardization, but the net, cumulative effect
should eventually enable DG developers to see significantly
lower interconnection costs; a smoother, streamlined application
process; quicker and more predictable project completion timetables;
and less reinventing of the wheel or redundancy.
FERCs recent ruling amplifies: Equipment manufacturers
will have compatible technical specifications to meet. New
generation will be located on the basis of what works best
for the Interconnection Customer and the Transmission Provider,
not jurisdictional differences in interconnection rules.
FERC also anticipates that Rule 2006 will, as the commissions
accompanying statement says, facilitate the introduction
of new technologies
limit the opportunities for transmission
providers to favor their own generation, preserve reliability
and safety of the transmission providers transmission
system
Other benefits include lower costs for
DG developers; enhanced grid reliability; increased energy
supply; lower wholesale electric costs due to increased supply;
and more non-polluting alternative energy resources,
FERC notes.
FERC versus NARUC
If theres any shortcoming to FERCs new rule, it
would appear to be the federal agencys limited jurisdiction,
which encompasses only OATT utilities. The majority of small
generators interconnect with utilities that arent subject
to OATT, and hence theyre not subject to rule 2006;
rather, they fall under state commission rules. Here, NARUCs
two-year-old model interconnection standardwhich closely
parallels FERCs and provided much of its inspirationmust
undergo state-by-state implementation. As previously noted,
FERC and NARUC both claim jurisdiction and have engaged in
an ongoing turf battle, which appears to be going NARUCs
way. Although strongly supportive of DG in principle, NARUC
wants the 50 states to retain local jurisdiction. For its
part, FERC points out that Rule 2006 largely harmonizes
many of the best practices interconnection rules recommended
by NARUC anyway.
Richard Brent, who is government affairs director for Solar
Turbines and was active on a team of small-generation advocates
negotiating with FERC, notes that the federal-state jurisdictional
issue has been a recurring complication. In discussing DE
lobbying efforts in 2004, he recalls, We got into very
complex discussions concerning both local and interstate
transmission, because most all DG is not technically
wired to run at transmission-level voltagesand yet,
he says, here we were negotiating about getting interconnected
to the transmission system. Thus, at some points during
industry strategizing, the question was raised about why the
DE industry should worry about such interconnections, i.e.,
Why are we here at FERC, he says, as opposed
to working at the state level? Defining the breakpoint
between transmission and distribution is a regulatory can
of worms to be avoided, he adds, but the DE contingency decided,
the reason why we wanted to be connected to the grid
is because we believe we can be part of a demand-response
initiative, he says. We can be part of a capacity
market in key places like California, PJM [Pennsylvania,
New Jersey, and Maryland regional transmission], and New England.
In such locales, DE has a role to play in easing bottlenecks,
and a federal interconnection rule would give the industry
access to a wholesale market enabling credit for customer-owned
capacity, and customer oriented demand-response, says
Brent, who is also a former chairman of the US Combined Heating
and Power Association (USCHPA).
At one point Brents industry colleagues found themselves
in three-way negotiations with FERC and NARUC. He recalls,
In an odd way, while FERC gave a commendable effort
to interconnect small DG 20 MW and underwhat it may
have done was to tighten up the NARUC standards so that we
can start to look for a uniform national standard for interconnection
that can at least be a guideline and could be adapted, as
appropriate, and adopted by a given state. With the
issuance of NARUCs interconnection model in 2003, he
says, I think were 85% of the way there.
So thats kind of a nice side benefit of our negotiations
for the year-and-a-half-plus with FERC.
DG Lighting Up ISOs and RTOs?
Whats the real impact, then, of FERC 2006 on typical
transmission organizations? Eric Laverty, an engineer with
the Midwest ISO or MISOa nonprofit independent transmission
operators group covering 14 states and adjacent Canadian provincesparticipated
in multiple FERC stakeholders meetings in drafting both the
large- and small-generator interconnection procedures. From
a transmission standpoint, he says, The FERC order covers
a whole lot of ground. There arent too many people at
any utility or ISO who know all of it, he adds, referring
to Rule 2003 covering 20-MW-plus generators. FERC is thus
allowing ISOs and RTOs an additional 30 days to implement
Rule 2006 and granting greater flexibility than it grants
to utilities.
Regarding the interconnection rules themselves, Laverty explains,
the preliminary study processes required under the new regime
are very similar, really to what has always been
done. The chief gain of standardization appears to be that
the DE applicant can now deploy the same generating equipment
anywhere that FERC has jurisdiction. Hence, If youve
got developerd whobr been working out in California
and they want to come here to the Midwest and locate a project,
the rules are now the same in both places, he says,
so we dont have to go over every nuance of the
procedures. Technical dissimilarities from project to
project will remain significant, however, because transmission
systems vary considerably depending on, say, a rural versus
urban locale.
As for small generator connections to MISO, Rule 2006 will
impact a large number of our projects, he suggestsperhaps
half of the wind generation applications alone,
not to mention other DG technologies, all of which would be
classified as small generators. MISO ISO receives interconnection
requests daily, he adds.
State Interconnection Rules: Easy to Dodge?
Although this spate of regulatory intervention appears to
be an improvement, recent reports in California and New York
illustrate how far short rulemaking can fall if the regulated
utility is bound and determined to thwart DG, come what may.
A case in point: In 20042005 the California Energy
Commission undertook an extensive review of Rule 21 with the
aim of resolving several shortcomings. Submitting testimony
concerning the proposed revision, Tecogen, a national DG developer,
reported a quite less-than-satisfactory experience in that
state, lasting several years. For example, despite their having
met all requirements of Rule 21 in order to qualify for simplified
interconnection without additional requirements, Tecogens
local utility partner, Pacific Gas & Electric
(PG&E), somehow managed to reject all of Tecogens
interconnection applications, comprising 24 cogen units for
15 projects, according to Tecogens public-record statements
to the commission. PG&E also insisted that Tecogen apply
extremely expensive redundant safety systems based
on PG&E designs. Moreover, several Tecogen projects were
halted mid-construction, and stranded in the field or
at the factory, the company claimed. Ultimately, a compromise
ensued, but Tecogens experience under Rule 21 was
financially devastating to all parties.
| |
 |
 |
|
Another unhappy California energy businessmanMark A.
Moser of RCM Digesters Inc., Berkeley, CAattempted to
develop four projects in the state, connecting digester-fueled
generators to PG&E, Southern California Edison, and San
Diego Gas & Electric. A big loophole in Rule 21 allowed
the utilities a supplemental review, effectively
negating Rule 21 access rights. Mosers four projects
became seriously delayed and, once they entered the process,
Moser received no timetables for work completion. The projects,
he said, received no outside review, and no referee
(i.e., the dispute resolution process failed each time). Moser
reported being invoiced exorbitant sums for connection services
(one bill came to $30,000 and another utilitys statement
was 1-inch thick, he wrote). When the utilities
performed identical equipment tests, resulting charges inexplicably
ranged from a low of $500 in one case, up to $7,000 in another.
After Moser called a community newspaper to publicize the
alleged mistreatment, his expense tab was revised downward
$40,000.
Proposed Changes
Taking such testimony into account, Californias energy
commission devised several proposed changes in Rule 21, which
were forwarded to the California Public Utility Commission
(CPUC) earlier this year. Four key areas covered in the revised
rule follow:
- Net metering projects will lose the meter.
The CEC prefers that utility payouts to DG owners be based
on estimated power output rather than on actual meter measurements.
This would eliminate the significant cost of metering (which
can be expensive and is borne by the DG owner). Californias
innovative concept may need to be revisited, however, if
billing disputes proliferate. Meters would still be required
if the DG project receives public funding incentives or
tariff exemptions.
- Utilities cant thwart net metering for combined
DG (i.e., a system incorporating both net-metering output
and non-metered output). Compensation is to be given for
both kinds of DG. Interconnection rules for networked DG
will be incorporated into a revised Rule 21 (with a draft
proposal due in December 2005).
- Dispute resolution will be fine-tuned. Mediation
by the CPUC; tighter timelines for resolution; and clearer
identification of decision-makers will be incorporated.
Utilities will be required to provide more detailed technical
justification to the DG owner, rather than simply asserting
a need to protect safety and ensure reliability,
as utilities like to say. For educational purposes and to
assist other DG owners, dispute case information will be
made public, subject to appropriate confidentiality safeguards.
- Cost-tracking of utility expenses will give CPUC
regulators better data on what utilities DG-related
costs are, to assist in future evaluations.
- Grid-interconnection application fees and grid-infrastructure
improvements should be paid for by the utility, with
the cost recovered through the distribution component of
utility rates.
On a final note, New York State also boasts pro-DG regulatory
policies, but again, utility practices can continue to make
interconnecting tough. As Solar Turbines product manager Chris
Lyons noted last year, Each utility has a number of
outs that they use as excuses not to conform to
that FERC standard. Example: in dealing with Con Edison
in New York City, Lyons recalls, We were having to look
at whole new turbine-generator package designs to accommodate
what they define as their short-circuit study requirements,
thereby rendering the interconnects totally different
than what weve been traditionally used to.
Thus, again, despite the Public Service Commissions
best efforts at standardization, New Yorks interconnection
rules somehow remain specific to their utility,
Lyons says.
Will FERC 2006 help? Perhaps so, he speculates. Since Con
Ed imports power across state lines, the utility should fall
under federal jurisdiction. Or then again, Lyons wonders,
Maybe theyll get around it; I dont know...
DAVID ENGLE, a writer based in La Mesa, CA, specializes
in construction-related topics.
DE - November/December
2005
|