|
Occuring less than two years after the September 11th attacks,
the August 14, 2003, blackout again pointed out our
vulnerability, says Neil Karr, head of project management
for ALSTOM Power Rentals (APR). Much of the entire region
of Ontario was hit, along with much of the Eastern Seaboard
of the US and Canada.
During the blackout, Karr continues our
generator units at the Ontario Energy Management project site
ran for three days as the main power grid steadily came back
online. Thus APRs Ontario Energy Management project
was able to do exactly what it was meant to dobe part
of a system that could supply peaking power during a time
of high demand for power.
Project Background
and Rationale
In April 2003, the local utility in southern Ontario started
looking for a significant amount of additional power generation200
MW of power or more. The power was to be distributed around
much of that region of Ontario. The reason for the project
was simply to provide additional power during periods of peak
electricity usage. It was really installed as a security
measure, or an insurance policy, says Paul Marcroft,
business development manager for APR, and to support
the existing infrastructure system during the peak periods.
To fulfill this need, Ontario Energy Management Inc. (OEM)
and APR were awarded a temporary power contract for Ontario,
Canada, for 20 MW. The customer, Ontario Electricity Financial
Corporation (OEFC), decided that the Transportable Tempest
gas turbine generating system could contribute to solving
their problem.
One other factor may have been that the elections were coming
up in a short while. I think, perhaps, the government
wanted to make sure that they didnt have any lights
out during this election period, suggests Marcroft,
that is my opinion, perhaps, rather than the facts.
But whatever the case, they wanted extra power to meet demands
during the peakswhether it was political or not.
It was to prevent rolling blackouts, adds Christopher
L. Hobbs, project engineer with Peninsula Engineering and
Ontario Energy Management. When the whole Eastern Seaboard
was hit by the blackout last August 2003, we were able to
run through the entire period. ALSTOM Power Rentals did a
very good job for us through the entire project. Almost all
the details of setting up their project were very much cookie
cutter in nature. The engines arrived July 24th and on August
1st we were putting full power into the grid. The total time
involved was one week. Says Hobbs, If thats
not unusual, then theres not anything unusual out there.
That is extraordinary. I challenge anybody, using as many
hours in the day they want, to meet my week.
There were other proponents selected during the bidding process.
They were all awarded with a contract, says Hobbs,
but for a variety of reasons, timing or whatever, they
could not deliver. Only three of these actually delivered.
We were one of the three. The other two proponents were multibillion-dollar-per-year
companies, Caterpillar and Trans-Canada Pipeline.
The decision to proceed with the project was made on June
6, 2003, by the Canadian government. Ontario Energy
Management did have some hiccups along the way, says
Hobbs, but fortunately none of them had anything to
do with ALSTOM.
When asked if there were any lessons to be learned from this
project, Hobbs says, I cant think of anything
in particular. It was a lot of work to put those things in
for such a short duration. But then again, those units really
are designed to be mobile and easily connectable. That it
all worked out so well was certainly a pleasant surprise for
us.
The governments expectation was to put in temporary
power generation, which would allow them to make it through
their peak generation periods, says Karr, This
was in the event that they lost one of their own units or
in the event that demand went too high. So what they ended
up doing was putting in several sites with generation capabilities.
In the blackout these enabled everybody to go online.
The APR equipment didnt actually run much at all. It
just sat there for the six months of the contract in anticipation
of a problem. So it was strictly a peaking plant. But
the fact of the matter was, says Paul Marcroft, it
was never really run very much because the high peaks never
materialized.
It was not a single-source setup, says Marcroft,
there were a number of different authorized generators
in the area that were successful in winning part of the project.
There were also several different technologies being applied
and ALSTOM was fortunate enough to get 20 megawatts.
The OEFC was the end customer, says Karr, We
partnered with OEM to provide generation. They [OEM] did the
transmission and distribution, essentially, and we provided
equipment as well as startup services. It was kind of a partnership
there. GE and Cat were in similar situations but with different
companies.
Project Requirements
On April 28, 2003, OEFCself-described as an agency
of the Province of Ontario responsible for servicing/retiring
the former Ontario Hydros debt and managing other legacy
liabilities...issued an RFP, for Provision
of Temporary Generation Resources in Ontario for the Summer
and Autumn of 2003. This request included a 30-page
document containing details on the requested services as well
as stringent physical requirements and submission guidelines.
This temporary generation facility was to be located somewhere
east of London, ONT, south of Owen Sound/Barrie, yet not on
the Niagara Peninsula. The site selected by OEM was in Hamilton,
on the McMasters University campus.
Major concerns and thus requirements disclosed in OEFCs
RFP specified that proposals include detailed descriptions
of the projects impact on air emissions, noise levels,
potential soil disruption or contamination, and containment
concerns of nearby water courses. Proposals needed to assert
that compliance was made to all federal, provincial,
regional or municipal governments.
Those submitting proposals also had to include a demonstrated
ability to comply with the requirements of the Environmental
Protection Act and the Ministry of Environment regulations,
policies, and standards. Other requirements included plans
for telemetry, fuel management and metering, as well as operating
and voice communication plans.
Since OEFCs stated deadline for all proposal submissions
was May 12, 2003a mere two weeks after it was issuedthose
companies trying to win the bid had a lot of work to do, very
quickly.
Regarding whether there were many other companies available
to complete this project, Karr offers, In smaller generation
there are quite a few people out there. But in what I would
call big power in the turbine area, there are really only
two or three players. Its a pretty limited playing field.
The technology is expensive and it takes expertise to install
and run itwhich the smaller players just dont
have.
Were there other options out there for this particular project?
Neil Karr has a fairly simple answer, As far as alternatives
to this project, the only one I can think of is if theyd
taken the risk and not installed it. But they took the other
option and went with having power generation to help them.
The OEFC and the Canadian government simply had to call us
to tell us whether to proceed or not and to choose a supplier.
APR and the Ontario Energy Management Project
OEMthe local, authorized Canadian power generation companywas
APRs customer. But the ultimate customer on the project,
as mentioned earlier, was OEFC. After their request for a
proposal was out, all bids were submitted by May 2003, and
the equipment needed to be operational by around July or August
of that same year. APRs contract then ran through a
six-month period until the early part of this year, and the
equipment was demobilized in February.
The McMasters University campus site was chosen mainly because
a natural gas pipeline and high voltage interconnect were
both in close proximity. The project was based on the outskirts
of the university campus.
There were three units to the project, located around the
fringes of the university campus. The whole system was installed
very quickly. As Marcroft explains, It was fast-tracked.
In other words the project stood basically operational within
only a few days from the delivery onto the site. Then we were
really on a call-out basis. If they anticipated that the equipment
needed to be run, then we would be there within a certain
timeframe. But ultimately we were responsible for 24-hour
local coverage.
The utility then would make predictions or projections as
far as trending. Things such as the weather for the previous
daygiven that there might be a particularly hot day
in the summer or cold day in the autumnwould indicate
if they may or may not have an issue. But, as APR discovered
throughout the contract, there was never really the demand
that was anticipated. Whether that means that theyd
had an especially mild summer and autumnwithout the
extreme heat and coldis difficult to determine exactly.
This was an interesting project for APR because they were
working very closely with OEM, the local company authorized
to actually do the project. APR could not deal directly with
OEFC. The reason for this was that APR was not an authorized
Canadian generation company. Thus OEM actually did the contract
with OEFC and APR was essentially back-to-back with OEM on
this job.
But we worked really closely with them on everything,
says Marcroft, and it went very well. The local generation
companies were tasked with locating a suitable site, and we
found that many of them had existing relationships with local
transmission companies, generating companies, and other outfits.
So what they had to do was locate a site that had a suitable
integration point into the grid, as well as access to fuel.
Fuel was very important. The Canadian government wanted the
project to be gas-fired because they wanted low emissions.
The local companies didnt just come out, get the
equipment, install it on the site and run it, says Marcroft,
they had to find a suitable site, obtain the permits,
and then get the fuel to that site. Though there were multiple
considerationsincluding fuel, permitting, and physical
spacea chief consideration was the interconnect point,
or how they were actually going to get the power onto the
grid.
APR provided OEM with the compact, transportable Tempest,
which was important given that the amount of space on this
site was relatively restricted. The three 7.9 MW (ISO) Tempests
were dual fuel, dry low emission (DLE) units that were efficient,
environmentally friendly, and reliable. Paul Marcroft says,
It really helped that APRs transportable Tempest
gas turbine generating system represents more kilowatts per
square foot than any other gas-fired technology out there,
which was critical because they wanted to squeeze as much
power onto that site as they could.
As Neil Karr points out, Our expected results in the
end actually matched reality fairly well. When we were called
to run, the units came up and ran nicely. During the blackout,
they really got what I would call their exercise. Canada was
fortunate in that period of time when all of this generation
was there that they really didnt need it at the end
of the day. They ran very seldom until the blackout. Then,
when the blackout occurred, thats when the units paid
for themselves.
There was a little bit of a learning curve when it
came to the differences between Canadian versus American regulations.
But I think as a team everybody pretty much worked it all
out and did very well.
No Major Problems or Hiccups
There were lots of variables that OEM had to consider. They
had to consider how many Tempests they could put onsite; they
managed to fit three. They also required gas fuel, which they
could get onsite, but had to rent a gas compressor to raise
the pressure, according to the requirements of the Tempest.
Then they had to look at transmission. The University of
Hamilton had an interconnect system into the main grid, so
OEM saw an opportunity that was local to where they wanted
to site the equipment. The power rental company did not supply
a transformer. I am not sure if OEM did or did not,
says Marcroft, but otherwise it would have been just
13.8 KV of voltage to have it up onto the transmission lines.
It was OEMs responsibility to take the three Tempests,
apply for environmental permitting for those Tempests, and
to obtain whatever permits it needed in order to get the equipment
in place. It was quite challenging for them. The OEFC
were stating, says Marcroft, this is how
much power we need and these are the key critical areas around
Ontario for distributed power generationwhat can you
do for us? It was particularly challenging for the local
generating companies involved.
APR bid its units to numerous different companies who were
looking at other gas turbines and small gas engines of all
different sizes for the same job.
The OEFC, however, was ultimately only looking for 200 MW.
So it was a close call for APR because it found itself bidding
to these different companies, but they only had a finite amount
of equipment.
There were a lot of subjective availabilities going
on, says Marcroft, and in the end we did get this
particular deal. It worked really well for us. There was a
lot of GE equipment, a lot of CAT equipmentgenerally
a real mixture of equipment up therebut in terms of
operation I dont think much of it actually ran at all.
It was just installed, sat there for six months, and ran for
a few hours. APR fast-tracks power into places that need it
for a temporary project. It was never meant to be permanent.
For this particular site it was just meant to cover their
peak period.
For APR there were some challenges with respect to logistics,
especially with the equipment. The equipment was coming out
of Houston, TX; so shipping it all up to Ontario was quite
a lengthy process
When it came time to work out the details of transportation,
the logistics team had to work closely with each state and
find out which were the most lenient in their rules and restrictions.
APRs equipment got routed through these states. The
equipment was successfully trucked to the site following normal
roads all the way to the Canadian border and then on into
Hamilton, ON.
These particular Tempest units are designed specifically
for fast trackingrapid installation and rapid start.
Thus, this wasnt the standard package. It was designed
to sit on virtually any foundation and, rather than taking
weeks to set up, would take a matter of days to have the units
up and operational. As the APR Project Profile describes the
setup, On delivery to site, the turbine and ancillary
equipment needed to be positioned on a level surface, but
no special concrete foundations were required.
A standard Tempest gas turbine generating package would take
in the region of four to five weeks to actually setup, commission,
and have ready for commercial operation. APR and OEM completed
the exercise for all three units in about a week. But it helped
that theyd been tested on APRs own site before
installation on their customers site. It was also the
first time theyd been set up and actually used in a
commercial application.
APRs Marcroft doesnt recall anything being a
major problem, either during the initial execution or throughout
the contract. There might have been some minor things
just during commissioning. But from what I can gather, all
three units were setup, installed, and operational relatively
quickly. I dont think there were any major issues along
the way and I dont know of any major hiccups with permitting
or anything at OEMs end.
In terms of the original scope of the project,
adds APRs Neil Karr, everything was pretty well
successful.
We werent prepared to run under blackout
conditions, because it wasnt in the original scope or
requirement of the units. When the blackout hit it took them
a little while to find a startup generator to black-start
these big units. That was a little bit of a problem. But we
did locate one locally, wire it in, and fire up the units.
The original scope or requirements of the unit werent
such to do that. Its not hard to doas long as
you know how. Nobody expected the whole grid to go black.
The blackout validated what they had done.
The nature of the exposure and the opportunity was
the greatest reward for us. That is our business model. Just
the reward of being chosen to do this job was reward enough
for us. The blackout just proved to be an opportunity to demonstrate
the capabilitieswhich we werent expecting to do.
In a world where blackouts and all sorts of other problems
are a very real possibility, temporaryand fastpower
generation is a necessity. The APR Temporary Power Project
with OEM in Hamilton, ON, proves it.
PETER HILDEBRANDT writes extensively on engineering
and scientific subjects.
DE - May/June 2005
|