Founded in 1999 by Dan Cashdan and four partners, including
two with energy-industry backgrounds, RealEnergy eventually
attracted $75 million in venture capital. But it was all gone
by 2004 when one of the partners, Kevin Best, bought the name
and intellectual assets. The 13 MW of physical assets the
company had built and installed were sold to DG Energy Solutions
of San Diego, CA.
What happened? According to a 2001 Wall Street Reporter story,
Chairman and CEO Cashdan was confident that the company's
"knowledge base, because we are technology agnostic,
will be the best real source of information. It's a dirty
sweaty business with screwdrivers and wrenches and hooking
things up. If we can't do it, none of these other engine
companies are likely to have much success."
Unfortunately, it was a basic misunderstanding of the "dirty
sweaty business" combined with poor engineering and maintenance
decisions that undid the company, according to interviews
with most of the partners and others in the industry. And
at least one distributed generation (DG) company owner said
RealEnergy's failure has had devastating impacts on the
industry, leaving venture capitalists and potential clients
distrustful of the distributed generation technologies and
companies still in the business.
As Steve Mueller, president of DG Energy Solutions, says,
RealEnergy "did things that defied gravity ... It raised
$75 million and the money's gone; we raised $40 million
and have 71 megawatts in the ground."
Cashdan admits to the loss. "By the time we were done
with it, we went through $80 million." he says. The experience
has left him angry. "The real estate community proved
very receptive to trying these technologies," he reflects,
referring to the gas-fired internal combustion engines and
microturbine systems RealEnergy installed. But in his opinion
the company failed for three reasons endemic to the industry,
and not with RealEnergy's performance, which others dispute.
The technologies RealEnergy usedprimarily Hess Microgen
and Waukesha engines along with two Capstone turbinesin
Cashdan's opinion never lived up to expectations. He
thinks these problems are at the heart of an industry that
has never worked. "I thought the cogeneration business
would be different," he says. The company's ability
to build and deliver energy according to its promises to the
underwriters was off by 50%, equivalent to a bond promising
a 10% return but delivering 5%, notes Cashdan.
The second reason Cashdan cites for the company's failure
was the rising cost of natural gas, which RealEnergy failed
to predict, coupled with engineering and construction problems
that did not allow the projects to operate at the specified
thermal efficiencies, which at times were as much as 80% off.
This equation caused the overall cost of power to be noncompetitive
with utility power. "It is cheaper as we sit here today
to buy power from the grid," Cashdan argues. To add insult
to injury, utility demand charges for one 15-minute period
could wipe out half a month's revenues. "As a result,
the cost of running the system can be more than its revenues,"
he adds.
The third reason for the sorry state of the industry, Cashdan
believes, is ultimately the lack of political will at the
federal level to make distributed generation successful. "The
government does not have time to look at a half-cent industry
compared to a vastly larger utility industry," he says.
In the end, Cashdan reflects, GFI Energy Ventures, the lead
venture capital company that first invested $50 million in
RealEnergy, could not have been a more patient and professional
partner, as were all the people who put money into the company.
Arden Realty, the Los Angelesbased office building owner
with 142 properties, was a tremendous client and very patient.
"We thought having the client and the money would make
it work," says Cashdan.
RealEnergy's business model was to produce onsite electric
and thermal energy that it then sold into its clients'
buildings. Systems ranged in size from 200 kW to 1 MW. It
leased space from the client in the building where the generation
system was installed. The system was sized to produce about
50% of the building's peak load and to displace peak
demand that would otherwise place stress on an already constrained
grid system. The systems were run, in most cases, 12 hours
a day, Monday through Friday, most Saturdays, and on occasion
on Sundays.
In his 2001 interview with Wall Street Reporter, Cashdan
emphasized that the demand was enormous, but that there were
no players in the distributed cogeneration market that owned
anything that approximated 100 MW. (That is not true today;
at the time of this writing DG Energy Solutions said it would
have almost 100 MW by the end of 2004.) Cashdan was being
realistic keeping the company's goal simple: At the time
it had 20 systems in various stages of construction. Apparently,
it was a real struggle getting those constructed and operating,
because it never got beyond 18 operating systems32 discretely
interconnected plantsthat in 2004 were sold to DG Energy
Solutions.
RealEnergy Reborn
Kevin Best, RealEnergy's current CEO and one of the foundersand
director of sales and marketing in 2001picks up the
technology story. He agrees that many of the plants RealEnergy
installed had difficulty holding to standards. It chose to
buy Hess Microgen engine packages because of the backing of
the parent company, Amerada Hess, a highly regarded East Coast
petroleum company, which moved into manufacturing. The company
trusted the name, Best says, but ultimately it trusted the
experts.
Best still supports the Hess Microgen packaged system. The
company purchased about 75 engines at $200,000 each because
of the high level of confidence it had in the manufacturing
process. The company is now evaluating Ingersoll-Rand's
250-kW microturbine for future applications because of its
ability to meet emissions regulations.
Best says the company is now requiring that equipment suppliers
meet performance standards through branding mechanisms and
that they perform rigorous testing. Engine service hours must
be realistic or the suppliers will pay significant penalties.
Emissions standards, which have become much more stringent
in recent years, are the biggest bugaboo, Best notes, because
the older equipment has had to adapt to much higher standards.
Gas prices escalated from $3.50/MMBtu to $6.50/MMBtu in the
four years RealEnergy built its systems. That was not on anyone's
radar, Best confirms. "Now
we'll plan for
volatile prices," he says. Best argues that electric
tariffs are needed to reflect wholesale/real-time gas prices
so that the industry can more equitably compete with utilities
that buy their fuel in October like everyone else and roll
their costs into rates a year later.
While Cashdan accuses utilities of monopolistic behavior
with the use of demand charges, Best thinks strategically.
Tariffs don't conform to distributed generation and in
fact are disincentives. "The utilities need us for half
of a daythe noon to eight peak periodand are competitors
for the rest of the time," he points out. If the electrical
and thermal load in a building requires that the system shut
down at 6:00 p.m., the customer will be hit with a $10/kW
demand charge. He discussed this issue in a meeting with California
Energy Commission commissioners. "We got a sympathetic
ear; they loved it," Best says.
Lessons Learned
Steven Greenberg, another partner who left RealEnergy a year
ago to form Distributed Energy Strategies (DES), says he is
taking another approach, based on what he learned while at
RealEnergy. "We look at energy facilities as though we
are mining," he says.
DES offers customers one or more of three choices: It can
teach them how to extract the energy resource; it can mine
the energy resource on a pay-as-you-go basis, allowing the
customer to benefit from the dollar savings; or DES can pay
for a license to mine the resource and keep the savings for
itself. This third option means the customer spends no money.
It is designed for those not comfortable getting into the
business of acquiring and maintaining energy assets, says
Greenberg.
Greenberg and other DG company owners explain that the economics
of the business depends on aggregating customer relationships
to create a pool of demand. It takes time to educate one customer.
The solution is to strike a deal with an industry association
or with one customer that has multiple sites.
For example, one of RealEnergy's original investors
was Arden Realty, the largest publicly traded real estate
company in southern California. RealEnergy installed an acre
of solar panels on the roof of Arden's 110,000-square-foot
City Centre office building in Fountain Valley. It went on
to install cogeneration systems in seven other Arden commercial
properties.
While at RealEnergy, Greenberg learned the importance of
having a consortium of vendors so as to not become dependent
on one supplier. The DG market is not a cohesive one, and
no one vendor can provide the equipment for all sizes and
fits, says Greenberg.
A Study in Contrasts
DG Energy Solutions, the two-year-old company that acquired
RealEnergy's 13 MW of operating DG systems, plus 9 MW
from Hess Microgen soon after, offers an insightful contrast:
At its height, RealEnergy employed 80 people in three offices.
DG Energy, with less money and more assets, has 55 employees
in California, New Jersey, Florida, and Oregon. DG Energy's
president, Steve Mueller, has 25 years of experience installing
cogeneration systems, which none of RealEnergy's principals
had.
DG Energy has a different philosophyit has chosen to
diversify its assets. It has 27 MW of operating DG systems
in hotels, office buildings, big-box retail, and campuses;
8 MW of cogeneration plants in industrial facilities; a 22-MW
equivalent in district heating and cooling systems; and 14
MW of biomass and other specialty generation facilities.
The company expected to close on another 18 to 22 MW of assets
by the end of 2004. And in 2005, it will start installing
critical energy systems to provide baseload power in data
centers and telecom facilities. DG Energy systems vary in
size from 500 kW to 2 MW, although a few supermarket systems
the company installed were as small as 140 kW.
Mueller says cogeneration technology has not changed in 25
years. It's all about economics, he observes, the effective
utilization of waste thermal energy. When a system is designed
with no effective round-the-clock, 24/7 thermal load and operateson
the averageonly 16 hours a day, five days a week, as
the RealEnergy systems did, it is tough to make the system
cost-effective. And it is 10 times more difficult to make
the units operate reliably due to the on/off nature of the
loads, he adds.
Instead, Mueller says, the company is restructuring the contracts
and re-tooling the RealEnergy systems it now owns to be more
baseload-oriented and to serve the 24/7 critical loads. He
likes the larger office building market and office parks where
the company can find 24-hour loads for both power and cooling,
such as the district heating systems he confesses he really
likes.
Regarding its difficulty with Hess Microgen and the poor
reliability of its packages, Mueller claims RealEnergy did
not have the packaging and engineering right. Furthermore,
communication with the servicing arm became contentious. DG
Energy has not had the same problemit owns 96 Hess Microgen
units along with some Solar turbines.
The design should be kept simple and easy to maintain, Mueller
stresses. When the units are operated 24/7, maintenance is
decreased. Turning them on and off daily only increases problems.
Maintenance is key and will lead to better reliability and
more profit, he says. Demand chargesthe problem that
plagued Cashdandisappear when the units serve the load
24 hours a day.
Three Views From Afar
Garrett Smith, president of Portland, ORbased Cogentech,
founded in 1999, says RealEnergy's implosion represents
the Achilles heel of the industry. RealEnergy attracted capital
and clients but its choice of technologies was poor, Smith
says. The result is DG companies have gotten a bad rap. The
general investment community is asking, "If this industry
is so good, why aren't the utilities interested?"
Smith reports. Furthermore, potential clients are telling
him, "We've heard about RealEnergy; we're not
talking." He says four or five projects were ready to
be built, and when the customers heard about RealEnergy and
its problems with Hess Microgen packages, they decided not
to go ahead.
"If we could have hooked up with the financial backing
and the corporate alliances [that RealEnergy had] there would
be no stopping us," Smith contends. He believes the utilities
will drive the industry once they rid themselves of the view
that DG is a threat. He cites Arizona Public Service as the
only utility in the country that has become involved in and
supports DG.
Compounding the economic difficulties most DG companies face,
many investment houses aren't interested in funding anything
less than $100 million, because the cost of capital is identical
even if they are funding much smaller amounts of $1 million
or $2 million typical of DG installations like Cogentech's.
At the end of the day, it's the scale, says Smith. Even
if the company has 6 or 10 projects, it's still not large
enough to attract venture capital funding, he argues.
Without that funding, DG companies the size of Cogentechits
core staff is 8 to 10 employeescannot attract large
corporations. The result is that Cogentech is installing projects
exclusively for private entities willing to put up the funding,
making it a feast-or-famine business and dependent on getting
new projects, Smith says.
Smith also suggests that venture capitalists are putting
their money into new technologies like fuel cells and new
solar technologies, precisely because they are new and sexy
and popular. When he talks of GE Jenbacher technology, for
example, "The VC guys fall asleep," he says.
Smith argues that had RealEnergy honestly evaluated the DG
technologies being used around the globe, the company would
have discovered that Jenbacher, with 40 years of experience
in Europe, had already proven out the technology Americans
are just now doing.
Furthermore, Smith says, Jenbacher is dedicated to its support
and maintenance. He said most packaging and service companies
have come out of the standby diesel generation industry. It
is very different from the DG industry where the natural gasfired
cogeneration systems operate 8,760 hours and have much more
complex control systems, such as utility grid interconnections.
The typical generation repair shop is clueless, Smith says.
Smith has seen the number of DG projects go down in the past
two years, and with the bad stories out there, he doesn't
know what the future holds for gas-fired combined heat and
power projects. Cogentech, an engineering and construction
firm, is now turning to renewable and biogas projects, he
explains. This includes anaerobic digesters for farmers, where
it will be easy to do 50 to 100 projects. In addition to state
incentives in both Oregon and California, Smith is in negotiations
with venture capital firms for funding for these projects.
Maintenance Is the Key
Len Beyea, a senior energy engineer and certified cogeneration
specialist at NORESCO in Santa Cruz, CA, with almost 20 years
of experience in the field, explained that maintenance of
cogeneration systems is important but expensive. NORESCO does
not maintain the cogeneration systems it installs and instead
requires customers to sign long-term agreements with an approved
service company.
Beyea says once the unit is installed operation is rough
for the first two to three months, primarily with control
problems. Once the bugs are worked out, the unit can be expected
to be trouble-free for two to three years, with 96% reliability
the first year and 86% reliability by the second year. "If
you don't realize this, you're headed for trouble,
he says.
Telecommunications has made a big difference in the development
of the industry. As opposed to 20 years ago, now when a unit
goes down it can often be diagnosed online, from across town
or across country.
As with Cogentech, Beyea says cogeneration units are being
sold because customers are requesting them. The systems have
long paybacks, 8 to 10 years even when California's self-generation
incentives are included. This works financially, but always
on the margin, he says. The reasons are the high cost of fuel
and construction costs. Furthermore, maintenance costs are
equal to or slightly higher than thermal savings. Add in time
to push the project through the permitting process, and this
size project500 kW to 1 MWbecomes quite expensive,
increasing its payback time.
Beyea admits he is generalizing and there are exceptions.
It will take gas prices going down or electricity prices going
up to make DG profitable, he argues, adding that a DG system
using a waste fuel, such as landfill gas, will look terrific.
Larry Tengel is vice president and general manager of Enercon
Engineering in East Peoria, IL, and chairman of the US Combined
Heat and Power Association. He describes RealEnergy's
business model as unique and describes the company as having
grown too fast. But the poor quality of the technology it
chose created many problems for it, in particular major backpressure
and overheating problems.
Tengel, who knows the team at RealEnergy, confirms the other
major problem facing the company was an underappreciation
for maintenance. Without these problems, its business model
would have succeeded, he says.
Enercon manufactures electrical systems and controls, and
packages cogeneration units from 100 kW to 5 MW for installers
such as Stewart & Stevenson, which no longer packages
the units. With installations in 90 countries, it has experience
handling maintenance issues.
The competency of field service technicians is an issue,
says Tengel, and more expertise is required than typical electrical
contractors have. Engines are a standard item, fairly easy
to maintain, while the control system and "balance-of-plant"the
valves, thermostats, heat, etc.require highly trained
technicians to maintain. But in the past seven years, Tengel
says, engines have gotten more complex. For example, a Caterpillar
technician cannot do much without his laptop. Diagnostics
now require computer analysis.
Furthermore, it's difficult to train field people how
to make repairs following troubleshooting in the office. The
solutions are costly, Tengel admits.
California-based LYN CORUM is a technical
writer specializing in energy topics.
DE - March/April 2005
|