The Los Angeles Department of Water and Power (LADWP) has
developed one of the most recognized distributed generation
(DG) programs in the US. In the last 15 years, over 125 MW
of DG have been installed, representing nearly one quarter
of new generating capacity for Los Angeles. The purpose of
the LADWP's DG program is to identify and encourage the
beneficial use of localized electrical generation to reduce
electricity load growth, defer or avoid electric utility infrastructure
expenditures, provide premium energy services to Los Angeles
energy consumers, encourage energy efficiency, and improve
the environment. To meet these goals the LADWP has created
four DG demonstration testing facilities to test various DG
technologies and the electric grid effects under various operating
scenarios. At one of these facilities, the LADWP has identified
a potential islanding problem, where two neighboring generation
sources can interact to create an unplanned generation island.
| |
 |
 |
|
What Is Islanding?
Most DG provides power to an onsite load while remaining connected
to a utility electric grid to take advantage of the flexibility
and reliability such an interconnection affords. Interconnecting
to the grid means that all the generators connected to the
grid must operate at the same frequency and at the same phase
as every other generator connected to the grid. Most DG units
that are tied to the grid are configured to shut down when
the grid does not generate power.
Configured to operate in islanding mode, DG units can continue
to provide power to onsite customers if the utility's
grid goes down, in which case the DG unit would disconnect
itself from the utility and continue generating power to the
customer load. This extra reliability that DG units can provide
to onsite load is one of the primary benefits of DG. The problems
of controlling islands and interconnecting them to utilities
are still limiting this option for many customers. So, although
DG devices can be configured to island, for the remainder
of this article we will assume that the customer/utility has
installed the DG devices in a manner designed to prevent islanding.
Potential Problems With Islanding
Unintentional islanding of DG has the potential to jeopardize
safety, disrupt reliability, damage equipment, and reduce
power quality.
Traditional generation and distribution companies' primary
concern of islanding involves safetythe risk that field
personnel may be injured due to the presence of unknown and
operational DG, and the risk that islanding may damage utility
equipment. This is of particular concern since the protection
equipment of DG is not generally maintained by the utility,
but by the utility customer itself. This may lead to a compromise
of the utility's protection scheme if the customer's
fault response is not adequately coordinated with that of
the utility. For example, if the DG does not clear a fault,
the utility may be forced to trip a wider area, thereby creating
a larger outage.
In a typical fault seen by a utility, a relay will detect
the fault and cause a breaker to open at the source distribution
station to de-energize the affected line and halt the flow
of current. Normally, the utility protection scheme is designed
to close the breaker after a few seconds to allow power to
resume if the fault has cleared. However, if the DG is not
separated from the grid, the DG-supplied current may resemble
the fault current and will prevent the breaker from closing
automatically. The DG must be able to isolate itself from
the grid during a fault before the utility fault response
closes the breaker. If the DG has isolated itself from the
grid and allowed the breaker to successfully close, the DG
unit may now be out of synchronism with respect to the grid,
and closing under such circumstances may cause severe equipment
damage.
Unplanned DG islanding could also damage customer equipment
by providing operating voltages or frequency outside state
regulatory standards. This problem can be avoided by incorporating
the appropriate generation-to-load ratio to establish the
voltage and frequency thresholds.
The islanding problems posed by DG have, for the most part,
been adequately resolved by DG manufacturers and islanding
has generally been limited to those times when the practice
is allowed by the utilityideally when the DG is disconnected
from the utility grid. To minimize potential DG problems,
all DG protection schemes should be effectively coordinated
with the utility protection scheme. Some relay settings for
a typical DG installation are given in the table.
The LADWP's Islanding Dilemma
As shown in the figure, the LADWP's Main Street Test
Facility has microturbines connected in parallel to a fuel
cell. These DG devices are connected directly to the utility
grid through an industrial station containing a circuit breaker.
In between the DG devices and the industrial station are various
loads.
To demonstrate that the DG unit can be safely disconnected
from the grid, before any DG device is commissioned, the LADWP's
line patrol mechanics conduct various disconnect tests. During
one such test, while a DG unit is delivering energy to the
utility grid, the mechanics switch the DG disconnect to isolate
the DG from the grid. The DG output is then measured to ensure
that the DG relays disconnect from the grid and that no energy
is delivered. This test demonstrates that the DG unit can
shut down safely when the grid is not providing power to the
fuel cell at the fuel cell disconnect point, as indicated
in point A of the figure.
If a fault occurs at point B, the breaker at the industrial
station (point C) will open, isolating grid power from the
fault. The relay settings in the table ensure that during
a fault at point A, the fuel cell relays will detect the fault
and cause the DG unit to stop generating power.
A potential problem occurs if there is a fault at point D.
Initially, the breaker at point C would open. Typically, the
opening of that breaker would introduce sufficient transients
so that both the microturbines and the fuel cell relays would
trip. However, even if the breaker at point C did not sufficiently
disrupt the circuit stability to trip the microturbine and
fuel cell relays, most likely the load connected to point
A would not have the matching power requirements by the grid
as seen by the DG devicesand this mismatch would cause
the fuel cell and microturbine devices to trip.
The problem occurs if the load (as measured by the fuel cell
and microturbines) mirrors the characteristics of the grid.
In this case, both the fuel cell and the microturbines may
continue to generate power to the load on the DG side of the
industrial station (point B). This is due to the fact that
the microturbine sees the power generated by the fuel cell,
interprets this as the grid being energized, and continues
to operatenot recognizing that it is islanding. Similarly,
the fuel cell interprets the power generated by the microturbines
as the grid being energized and continues to operatewithout
recognizing that it is islanding.
This problem is typically avoided when traditional generation
is employed because there is usually an industrial station
located at point A that uses relays to isolate the load from
the generation. Requiring customer stations to have similar
relay schemes would make most smaller DG installations prohibitively
expensive.
The LADWP's Proposed Solution
The LADWP addresses the unintended islanding problem by installing
a load-interruption device, located at point A, designed to
open when the breaker at point C is opened. This would prevent
the DG from continuing to feed the connected load, once the
DG is isolated from the grid. As previously discussed, a fault
at point A is already handled by the DG relays so the proposed
load-interruption device need only handle load current and
can be relatively small (as compared to devices that would
need to handle fault current). The load-interruption device
would most likely be a motorized disconnect switch.
 |
The breaker (point C) and the motorized disconnect switch
(point A) could be linked by radio or microwave transmitters
(depending on how far away the two are) so that when the breaker
opens the motorized disconnect would open. Note that the converse
should not be implemented because the motorized disconnect
should be manually closed after the breaker is closed and
the DG is synchronized back to the system.
Protection coordination would need to be modified with the
installation of the motor-controlled disconnects. Some utilities
set closing at 2 seconds, which is too fast for these motor-operated
isolation devices. The LADWP sets its closers at 5 to 10 seconds
for 34.5-kV feeders and 30 to 45 seconds for 4.8-kV feeders.
Afterward
In the example above, we proposed solving the potential islanding
problem by installing a motorized disconnect at the DG facility's
connection to the grid. This motorized disconnect would be
activated by a transfer trip from the industrial station breaker
feeding the circuit in which the DG facility resides. Installing
this fix at this site is feasible since the DG testing facility
was designed to be flexible enough to allow for this type
of modification. However, many customer sites are not fed
from an industrial station, but rather from a customer station.
Molded-case circuit breakers used in these customer stations
typically lack a relay and may lack the external capability
to incorporate transfer tripping. In these cases, the solution
outlined in this article would need to be modified around
onsite peculiarities.
References
Brown, R.E., J. Pan, X. Feng, and K. Koutlev. 2001. Siting
distributed generation to defer T&D expansion. IEEE PES
Transmission and Distribution Conference, Atlanta.
IEEE guide for protective relaying of utility-consumer interconnections,
unapproved C37.5 draft 6. 1999.
Kirby, B., and N. Lenssen. 1999. Shifting the balance of power:
Grid interconnection of distributed generation. E Source,
October.
Mozina, C.J. 2001. Interconnect protection of dispersed generations.
IEEE PES Transmission and Distribution Conference, Atlanta.
Van Holde, D., R. Dugan, and R. Zavadil. 2002. Interconnection
guidelines for distributed generation. Multi-client study.
E Source, August, and Electrotek Concepts.
ROBERT CASTRO is customer generation program manager
for the Los Angeles Department of Water and Power. He is also
professor of power engineering at the University of Southern
California Graduate School of Electrophysics.
DE - March/April 2005
|