|
In 1995 the University of California at Irvine and the Irvine
Company started planning University Research Park, which would
integrate the infrastructure needed for distributed generation
(DG) into its 40 buildings as they were constructed. The 185-acre
park was designed to attract high-tech e-commerce, biochemical
and biomechanical businesses, and energy technologies.
According to Scott Samuelsen, director of UCI's National
Fuel Cell Research Center, the "Power Park" was
to serve as a living laboratory and test bed for the various
technologies of DGmicroturbines, fuel cells, microturbine/fuel
cell hybrids, cogeneration, and photovoltaicsin a real-world
evaluation.
By 2000, the park was half-built and the developers assumed
it would be completed in two or three years. However, today,
just seven more buildings have been added. The Irvine Company
says it will construct new buildings as the market dictates.
Clustered in gently rolling landscape at the southern end
of the Orange County campus, the 28 two-story, rectangular
buildings built to date are based on one "flex-tech"
design, each 30,000 to 70,000 square feet, created by the
design firm LPA Inc. of Irvine.
Designed for
Flexibility
Architect Jim Kelly says the buildings
are constructed as shells to allow tenants to design their
own interiors. The infrastructure was designed for flexibility
to allow different configurations of DG to be tested, once
systems are installed, with alternative distribution options
and multipoint monitoring of power quality.
Underground electrical conduits link the buildings across
the park. Two buildings are connected through conduits, giving
a tenant the opportunity to occupy both and to link telecommunications
and electronic systems. The underground conduits then connect
the building clusters to other clusters across the park.
Electrical rooms in each building serve as the connection
points for the conduits. The rooms are built larger than is
typical to accommodate switchgear and other electrical equipment
required for future microturbine or fuel cell installations,
Kelly says.
The research park is within service territory of Southern
California Edison (SCE). The utility took a big interest in
the design of the buildings and served as technical consultant,
meeting with representatives of the design team every month
for six months, says Stephanie Hamilton, manager of SCE's
distributed energy resources department. "We shared with
them our expertise to make sure equipment would be compatible"
with SCE's system interconnections and distribution lines,
she says. Its recommendations included installing additional
conduits and cables, and it provided equipment to measure
power quality.
Kelly, the architect, explained that natural gas distribution
was a simpler proposition. Southern California Gas Co. installed
4-inch main lines and 2-inch service lines to guarantee each
building has the capability for up to 500 kW of natural gaspowered
electric generation. These installations were larger than
normal to accommodate anticipated loads. In normal circumstances,
a 3-inch main and 1-inch service line would have sufficed,
according to the company.
Additional design elements were included to benefit DG installation.
Electrical conduits run through the roof of each building
to allow future tenants to install photovoltaics. Kelly says
LPA assumed the photovoltaic panels would lie flat on the
roofs, as they do at the Toyota headquarters in Torrance,
which the company also designed. Furthermore, zones were identified
around each building, 40 feet by 80 feet, to accommodate microturbine
or fuel cell generation equipment.
Where's the DG?
Despite
the good design and intentions, no tenants have installed
DG systems beyond a few backup generators. In 2000, Samuelsen
expected a 30- to 75-kW microturbine generator or a 200-kW
fuel cell to be installed within the next six months. But
those installations did not happen. Now, he says, two new
prospective tenants, a computer engineering company associated
with information technology and an architecture and green
building design firm, are both considering DG installations,
but they have not yet made any commitments and it is too early
to identify them. So what happened?
Samuelsen blames California's recalcitrant economy, the end
of the energy crisiswhich had fueled interest in DGand
lack of enabling policy to encourage and facilitate distributed
generation as the reasons behind DG's lack of growth in the
research park.
Eric Ring, manager of energy engineering at CTG Energetics
Inc. in Irvine, has a different take on the issue. Speaking
in general, not specifically about the research park, Ring
says DG is typically found in owner-occupied buildings, not
in buildings where the occupant is leasing floor space. In
the latter case, tenants have little incentive to install
equipment they cannot take should they move. Nor does the
property owner have any incentive to install DG, since he
or she has to recoup costs in rent. And there is a disconnect
between capital and operating costs, says Rink. Often, the
owner will negotiate a tenant allowance but is unwilling to
go beyond that allowance to pay DG costs.
And why are tenants not motivated to pay the additional costs
for DG? Ring argues the office tenant is not used to seeing
energy expenses or to paying attention to them. There may
be a tremendous opportunity to reduce costs, but they're
not on the tenant's radar screen. Moreover, the tenant
may benefit from generating his own power, but often he has
little or no need for use of the waste heat from the microturbine,
which is often the difference between a small and large payback.
Ring points out an additional disincentive: Utilities may
discourage DG because of fears the power may be low-grade
and disrupt distribution in the local utility line through
the connection with the distribution line linked to the building.
Conceptually, this can be worked out, Ring says, but interconnection
agreements can be difficult to negotiate.
Kelly agrees that tenants lack the same incentives owners
have to make the buildings they occupy as efficient as possible.
He says tenants could take DG equipment with them when they
moved, but the investment in installation could not be recouped.
And the Irvine Company, the owner of the research park, has
not made any capital investment in DG, he says.
Interviews with managers at two tenant companies in the research
park reinforced Ring and Kelly's perspectives. Dan Matyja,
IT operations manager for Quantum Corp., says the company
was going to install microturbines in September 2001, but
budgets didn't allow it. The company, which sells computer
data storage products, needed backup generators to protect
the company's data center, especially during the period
in 2001 when there were four-hour power outages.
"Microturbines had many benefits but for the amount
of power we needed, they were quite expensive," Matyja
says. With microturbines, the company could have sold power
back to the utility, but company executives were not willing
to do the cost/benefit analysis, he notes. It was more important,
they decided, to get backup generators installed quickly.
Matyja agreed that not owning the building was a factor. "If
we had owned the building, we could have seen a payback,"
he says.
Jake Lappin, technical services manager at Monitoring Automation
Systems (MAS), a software company, says MAS has been a tenant
in the research park for six years. It never looked at DG,
but wanted to have backup power. So it installed a diesel
generator without exploring other technologies. When the company
moved to a new location in the research park, it left the
backup generator behind. Lappin says a short-term battery
backup is serving the company well and provides two to three
hours' service in case of a power outage.
Overcoming the
Hurdles
Samuelsen's dream that the research park
could serve as a real-world testing pad for different DG applications
will become a reality only when those disincentives and other
hurdles are overcome. Jim Meacham, a graduate engineering
student working in the National Fuel Cell Research Center
at UCI under Samuelsen, adds to the list of hurdles lack of
familiarity with DG technologies and a true lack of a service
sector for them. "We're just learning what systems will
work in a commercial building where the electrical loads and
thermal demands are highly dynamic," he says. For starters,
Meacham has installed interval meters at many of the buildings
and reports monitoring power usage has already provided some
information.
On the regulatory side, Samuelsen points to "a lack
of policy to underwrite DG's evolution." On the
one hand, utilities fear the potential of DG to disrupt power
distribution and leave assets stranded. On the other hand,
the California Public Utilities Commission believes DG is
an effective way of reducing peak demand and deferring distribution
system upgrades. It has offered rebates for self-generation
projects for several years. Although the rebates reduce installation
costs, they do nothing to remove barriers.
Regulatory Solutions
In
February 2003, the California Public Utilities Commission
established policies for ownership and operation of DG and
its integration into utility planning and operation of the
distribution grid. It said the utilities (SCE, Southern California
Gas, Pacific Gas & Electric, and San Diego Gas and Electric
Co.) as well as third parties could own DG.
Given that utilities are concerned about the impact DG will
have on the reliability and safety of their distribution systems,
the decision focused on that area and told the utilities how
they should evaluate DG alternatives with regard to their
system planning processes.
The decision directed utilities to develop model contracts
that would allow DG systems to defer distribution system upgrades,
to track their costs, and to allow compensation to third-party
owners of DG systems that deferred distribution system upgrades.
It also directed the utilities to design DG education programs.
Perhaps this compensation is the carrot that owners of leasing
space need to install DG systems in their buildings. First,
however, utilities must decide which parts of their distribution
system would benefit from DG, and how much they are willing
to compensate owners to build these systems. Is it possible
SCE could decide its Orange County distribution system would
operate with less congestion if the Irvine Company installs
microturbines and photovoltaics on the majority of the park's
buildings and be compensated for it? Would this postpone or
avoid expensive distribution system upgrades? Could SCE afford
to decide that paying for DG systems would be less expensive?
It likely will take years for SCE or any of the utilities
to reach this decision-making stage, given the slowness of
the regulatory process. Meanwhile, educating tenant companies
about the advantages of DG seems to make the most sense in
the short term.
California-based LYN CORUM is a technical
writer specializing in energy topics.
DE - January/February
2005
|