|
The year was 1992: Wayne's World was sweeping movie theaters; Nirvana still had a front
man; Tiger Woods was a high school sophomore winning his second
Junior Amateur title; greenhouse gases were at some of their
highest recorded levels; and Provenant Health Partners of
Denver, CO, was about to embark on a project to transform
its semipermanent emergency room structure in Frisco, CO (altitude
9,200 ft.) into a larger, permanent surgical medical center - a
project that would win national acclaim from the United States
Department of Energy (DOE), the Colorado Energy Conservation
Network, the American Council of Engineering Companies, and
the American Society of Heating, Refrigerating, and Air-Conditioning
Engineers (ASHRAE), for its technological advancement of energy
and environmental design. Summit Surgical Center's evaporative
cooling system, designed by Beaudin Ganze Consulting Engineers
Inc. (BGCE), continues to operate today - a demonstration
of how creative synthesis of climatic conditions, functional
requirements, and energy and environmental goals can produce
better, cleaner, and cheaper mechanical
electrical plumbing systems.
Provenant's importance comes into
sharper focus when one considers that it serves four ski resorts
in the valley and that the nearest hospital is a lengthy ambulance
or helicopter ride away, not always a minor feat when subject
to the extreme weather conditions frequent in the Rocky Mountains.
The challenge of the center's 1992
transformation included preserving the continuity of emergency
medical services provided by the existing clinic, and was
compounded by strict hospital guidelines for surgical suite
temperature (65°F). The Colorado State Department of Health
(CSDH) guidelines stated that operating rooms must be maintained
at 50% relative humidity (RH). The site altitude of 9,200
ft. (2,804 m) above sea level and 50% RH requirement posed
a potential for condensation on the operating room's
exterior wall surfaces and glazing. BGCE's psychrometric
analysis corroborated this concern, and a variance was submitted
to and granted by CSDH to allow the maintenance of 35% RH;
however, the mechanical system was designed to provide the
50% RH should the variance be changed by CSDH.
 |
The center was designed with energy savings as its primary
goal; consequently both the mechanical systems and the building
envelope were designed to be energy misers. The original emergency
room clinic had continual complaints of inadequate space-temperature
comfort. Most were attributed to the age and unreliability
of the equipment. The owner requested that an environmentally
sound, energy-efficient heating and cooling system be designed
and installed within construction and operating budgets. The
mechanical and electrical systems enable the remote mountain
surgical center to be completely self-sustaining for up to
14 days in the event of a utility outage.
The new indirect/direct evaporative air-conditioning system
design is free of chlorofluorocarbon refrigerants. The approach
was unique for a surgical facility. Utilizing the favorable
high-altitude and climatic conditions of summer outdoor design
temperature of 77°F (25°C) and the low RH of 31%,
cooled air is provided to the surgical rooms at 54°F (12.2°C),
meeting strict hospital guidelines.
The Heating, Ventilation, and Air Conditioning (HVAC) system air stream is evaporatively cooled in
a two-stage process with both stages rejecting building heat.
The first stage is an indirect
process, during which airflow passes through a cooling coil
containing evaporatively cooled water. The water is cooled
by a rooftop cooling tower in an evaporative cooling process
and then piped to the coil. The air stream does not come in
contact with the water. In the second process, air comes in
direct contact with cold, potable water that is evaporated
in the air stream, further adiabatically cooling the air to
54°F (12.2°C). The air then is ducted to the surgical
suites, resulting in a 65°F (18.3°C) air temperature
at 50% RH.
 |
Humidity is added to the air stream via an innovative method.
The direct evaporative cooling section of the air handler
is equipped with a sump heater, and during the winter months,
when humidity must be added to the air stream, the evaporative-cooler
sump water is heated and pumped through the evaporative pad.
The air stream is filtered to 35% average efficiency per ASHRAE
Standard 52-76 at the central air handler and to 90% at the
operating rooms. This also meets the 1993 edition of the American
Institute of Architects "Guidelines for Construction
and Equipment of Hospital and Medical Facilities."
| |
 |
 |
|
The new and enlarged facility's single air handler supplies
17,500 cfm (8,258 L/s) to the building, while 5,100 cfm (2,407
L/s) (29.2%) is outside air. A slightly smaller airflow is
continually exhausted from the substerile areas, the laboratory,
and the restrooms for ventilation and to maintain positive
building pressure. Air balancing was critical to ensure that
the surgery suites maintained the proper space pressure with
respect to adjoining areas. ASHRAE Standard 62-1989 is either
met or exceeded in all areas of the facility as demonstrated
in Table A.
 |
The seven refrigeration compressors and seven condenser fans
were replaced by one supply fan, two pumps, and a cooling
tower fan, even though the facility's square footage nearly
tripled. The old and unsightly air-conditioning units located
on the ground were removed. The new mechanical equipment was
contained in an enclosed building, and the clean lines of
the cooling tower on top of the equipment room go virtually
unnoticed from the ground level.
A direct digital control (DDC) system, which also acts as
a remote monitoring system, was installed, allowing the parent
company, based 100 mi. away, to monitor it. The DDC system
controls the daily flush for the evaporative-cooler sump to
minimize biological contamination. It controls the tower drain-down
function to prevent equipment freezing, a major concern in
the mountain environment.
The new system addressed ASHRAE Standard 55 for occupant
comfort and eliminated such complaints. The building shell
exceeds ASHRAE Standard 90.1 by prescriptive method and is
demonstrated in Table B. The only augmentation of the system
was adding auxiliary cooling coils just to provide redundant
coverage for the worst-case scenario days.
Costly, inefficient, and environmentally unsound refrigeration
equipment was replaced with cost-effective equipment. The
original clinic equipment used 1.4 kW of electricity per ton
of cooling. The new system was designed for 0.3 kW/ton, or
5.9 kW (0.5-, 0.75-, and 3-hp motors) input, translating into
a direct energy savings of 79% on a per-square-foot basis.
Review of the 1994-1995 electrical utility data (Table C)
clearly demonstrates that summer cooling had virtually zero
impact on the electrical demand and consumption. There is
no historical electrical demand data for the facility since
the previous electrical service was only metered for consumption
(kilowatt-hours).
The
indirect/direct evaporative cooling system serving this surgery
facility provides not only operational cost-savings but also
installation savings. This surgical facility addition/remodel
was slated for 20 tons (70.4 kW) of cooling, but due to the
altitude effects on equipment capacity duration, a 25-ton
(88-kW) air-cooled chiller would have been required. Utilizing
the indirect/direct evaporative cooling system resulted in
an installation-cost avoidance of $10,500 when compared to
a conventional system.
The new indirect/direct evaporatively cooled system is
less complex and has far fewer moving parts, which results
in less maintenance. The replacement of the original seven
packaged, air-cooled, air-conditioning units with the evaporatively
cooled system enabled the director of plant operations to
reduce the number of site-maintenance personnel. The old air-cooled
units demanded constant attention and required that a certified
refrigerant technician be called upon if repairs dictated
removal or replacement of refrigerant charges. The recommended
replacement interval for the direct-cooling evaporative media
is two to three years at a cost of $1,200. The indirect coil
requires biannual waterside cleaning, which is a 12-hour job.
By all accounts, Summit Surgical Center was an example
to be held up for other medical service providers to consider
when upgrading their campuses. And so it was.
The year was 2002: Mike Meyers again was sweeping movie theaters
but this time as Austin Powers; Nirvana now was something
one sought at yoga class; Tiger Woods had become one of the
biggest icons in the history of professional golf; greenhouse
gases threatened the environment at ever-increasing levels,
and another medical services provider, Arkansas Valley
Regional Medical Center (AVRMC) in La Junta, CO, was poised
to launch its central plant renovation project - a project
that would catapult it from the vestiges of its hodgepodge
of systems, including a vintage 1950s plant, to twenty-first
century operating capabilities and efficiencies, including
allowances for a future cogen system and equipment, should
effective utility rates warrant system conversions.
 |
AVRMC is an amalgamation of an 80-bed hospital, a medical
office building, and two nursing-home wings, the original
facility having been added to at numerous junctures and the
existing physical plant having been divided between two areas
of the campus along the way. A more recent addition included
adding mechanical/electrical physical plant capabilities to
help serve the new wings but left the outdated physical plant
to serve the existing buildings. The newer wing of the hospital
was equipped with a 350-kVA emergency generator but received
its heat from the outdated physical plant. The 1950s vintage
plant, equipped with steam boilers, a single 300-kW cogeneration
unit (a venture from the early '90s) and a 208-V emergency
generator that served the hospital's emergency power load,
had expended its useful life. So BGCE set off to merge the
old and the new, once and for all.
The existing cogen unit engine carried a life expectancy
of about 10,000 hours. With 8,760 hours in a year, that meant
that their generator would barely make a year before they
would have to take it down and rebuild it. The day they took
it down for rebuild, their electric demand would spike, and
they would set their electric rates for the next year. Since
rates for the coming year are set based on current-year peak,
they were not able to earn the lower rates their system should
have been earning. If they had had a backup generator, even
if it was not a cogen unit, they could have taken the cogen
unit down and put this other one up to avoid those demand
charges.
 |
 |
The team explored reutilizing existing cogen equipment and
peak-shaving opportunities. The hospital's current gas and
electric rates did not warrant the use of cogeneration; however,
there were significant advantages to reusing the old generator
instead of shipping it off to the salvage yard. It was adequate
in size to power an electric chiller and thus provide peak
shaving and demand avoidance to the medical campus. Also,
should the main generator for providing emergency power lapse
for whatever reason, that repurposed generator could offer
additional backup. The goals of the new design included having
a plant that could be set up to accommodate cogen functionality
in the future should the gas and electric rate structure shift
to make cogen economically desirable.
The new construction project, to be completed in the spring
of 2004, has included a new steam boiler plant, a new emergency
generator for the site to handle all emergency loads, an absorption
chiller coupled with an existing electric chiller, and reuse
of an existing generator designed with power feed to serve
the electric chiller. Additionally the chiller plant was selected
to strategically utilize steam-absorption chillers and electric
chillers so the owner could operate the plant to utilize the
most cost-effective energy source, be it gas or electricity.
With gas currently being the most economical fuel, the primary
cooling for the expansive campus will be from the absorption
chiller system. Any necessary additional cooling that the
absorption chiller cannot handle will be addressed by the
electric chiller, and that electric chiller will be powered
by the onsite generator, thus avoiding the electrical demand
charges of the electric chiller on peak cooling days. This
unique strategy also allows for change to the chilled-water
generation approach based on utility rates. Should electricity
become a cheaper fuel source than gas, the electric chiller
could be utilized at the first stage of cooling.
The
decision of when to switch between the electric and the absorption
chillers involves analysis of the constant and shifting loads.
It is determining when there is enough load out there to baseload
the absorption chiller. There are other buildings on the campus
that use electricity but are not hooked to the central plant.
They have refrigeration equipment and are going to utilize
their equipment in the summer, so they are establishing some
of the amount of electricity used for their air conditioning.
In the wintertime, the load profile will shift such that a
portion of the load is simply coming from different draws;
therefore in wintertime the system only needs to shift for
the fraction of the increased load to the system's plants.
That is why we can run our central plants electrically for
many months of the year. There is a certain point, however,
when their loads start to climb. There is a certain cut-off
point where we say, "All right, time to stop cooling
with our electric chiller in the central plant."
The systems have been designed so if a big enough rate
spread in gas to electric rates develops - i.e., if cogen
makes sense - the owner easily could integrate the required
equipment. The hospital is a good candidate for cogen since
it has a variety of heating loads across all of the autoclaves,
sterilizers, domestic hot water, and kitchen requirements - there
are a lot of places to utilize waste heat - that add to
produce a fairly solid baseload, but cogen should be sized
to utilize all of the waste heat. This campus could benefit
from a small cogen plant on the order of 240 kW. Cogen units
are available in 60-kW units, so four 60-kW cogen units would
work nicely. This also would respond to the lesson learned
from the previous cogen equipment. It is nice to go with modular
generators so if you lose one, you are still operating at
75% power. If you base your economic model on three out of
four running, you can accommodate having one down for repair
and avoid the load spikes that impact your annual rate contract.
There
are some expenses associated with designing in the flexibility
to convert to cogen. The biggest premium is in the space.
You do not necessarily have to provide the space, but you
at least must identify where to expand the building to create
that space. AVRMC built in that extra space, as they had an
immediate space available. The space is adjacent to the plant,
so when the time comes, AVRMC can move its storage out, and
it is easily able to recast the space and integrate the systems.
Another cost associated with building in the flexibility to
convert to cogen was planning for how the electrical switchboards
were configured to allow for easy tie-in later.
 |
The project has posed the complex challenge of constructing
a new plant while maintaining the existing steam-heating and
chilled-water systems. The old chilled-water system included
electric chillers in the old wing and an electric chiller
in the newer wing. The existing distribution was a confusing
web between the existing plants and the various facilities
connected to them throughout the campus development. The new
distribution plan required increased capacities in some locations
and design of new cutovers to pick up old loads electrically,
steam-wise, and chilled-water–wise. Significant piping
reconfigurations were necessary to consolidate the plant into
one location, all the while keeping in mind the importance
of minimizing hospital downtime. Consolidation of the emergency-generator
loads required the use of temporary generators and reconfiguration
of the power system to change over the system, again to minimize
downtime. Plans also have entailed how to decommission the
old plant and how to take it off-line, making sure that the
new plant is really operational with no bugs or hiccups and
that it really works as intended.
The next year will be a process of learning how to optimize
the system, utilizing the DDC system with trend history and
the optimization capabilities in the DDC programming. The
first set-points and changeovers will be determined by engineering
modeling. After that, the team will be trend logging, analyzing,
and adjusting when to turn on the electric chiller, turn on
the electric generator with the chiller, and so on. There
are many variables in these algorithms. A lot of it is how
the building actually responds, whether it is a weekend or
a weekday, and what season it is - all of those real-life,
real-time conditions that dynamically drive demand. For example,
in the middle of wintertime, the team still might be able
to run that electric chiller off the grid. There might be
a certain point in time where the other 8 kilos on the campus
are starting to ramp up and the team all of a sudden needs
to stop using that big electric chiller and push right into
the absorption chiller. Going forward, the team also will
continue to analyze current utility rates and contracts for
the opportunity to initiate cogen operations.
BGCE looks forward to the next 10 years as an opportunity
to further creative development of systems for medical-campus
utility design.
DENIS M. BEAUDIN, P.E.,
is president and cofounder of Beaudin Ganze Consulting Engineers
Inc., a full-service mechanical, electrical, and plumbing
engineering firm with offices in Vail, CO, Denver, CO, and
Lake Tahoe, CA.
DE - May/June 2004
|