|
Welcome to Legal Brief. It is a pleasure to be a part of
this timely new publication. In each issue of the magazine,
this column will discuss legal and regulatory developments
impacting distributed generation. To that end, I welcome comments,
questions, and suggestions from our readers. I can be contacted
at the mailing address for DISTRIBUTED ENERGY or by e-mail
at flgreenberg@flglaw.com.
To place distributed energy in context, let's look back 25
years to when US Congress enacted the Public Utility Regulatory
Policies Act of 1978 (PURPA), the law that jump-started distributed
generation. Before PURPA became law, it was difficult, if
not impossible, for an electric consumer to install and operate
a generating plant to meet onsite needs. Electric utilities
were not obligated to connect customer-owned generation to
the utility system. Backup service was either unavailable
or available at a cost intended to discourage the installation
of a customer-owned generator. Electric utilities were unwilling
to buy excess electricity that customers generated but did
not need. PURPA addressed these barriers to the development
of distributed generation but only for cogeneration (also
known as combined heat and power) and renewable technologies.
PURPA was only the beginning. In the years since 1978, state
and federal laws and regulations have expanded the opportunities
available to distributed generation of all technologies, not
just renewables and cogeneration. Today a utility customer
who generates electricity can obtain transmission service
to sell that electricity to another utility or into a regional
marketplace for wholesale electricity. In some states the
nonutility owner of distributed generation can supply electricity
to retail customers.
The power blackout that affected the eastern third of the
US on August 14, 2003, highlighted the value of distributed
generation. Even before the blackout, state and federal agencies
had begun to consider ways to make it easier to interconnect
distributed generation with the local utility.
Interconnection typically begins with a request to the local
utility for interconnection. The request leads to a utility
study of the impact of the new generation on its system and
any new equipment the utility deems necessary to ensure safe
operation of the interconnection. The customer proposing the
new generation is asked to pay the cost of the study and any
equipment the utility requires. Before the new generation
can begin operation, the utility and customer sign an interconnection
agreement that governs the generator's operation and includes
provisions such as insurance requirements for the owner of
the generator.
In July 2003, the Federal Energy Regulatory Commission (FERC,
that regulates the wholesale interstate electric industry)
issued a Notice of Proposed Rulemaking intended to standardize
interconnection agreements and procedures for utility interconnections
with small generators no larger than 20 MW in capacity. Expedited
procedures were proposed for facilities no larger than 2 MW
and facilities between 2 and 10 MW. Time limits were established
for utility responses to interconnection requests, and a regional
queuing process was proposed for utility processing of interconnection
requests. The proposed rule provides for three levels of processing
an interconnection application: super-expedited, expedited,
and standard. The categories are based on facility characteristics.
For example, a small generator no larger than 2 MW comprising
equipment precertified by a national testing laboratory as
meeting applicable industry and safety standards would bypass
design review, testing, and other steps in the interconnection
process and would be eligible for a highly expedited interconnection
process. Eligibility for expedited processing also depends
on the impact of the proposed facility on the interconnected
system, based on proposed criteria and on the concern of the
interconnecting utility about the impact on the utility's
(or other transmission provider's) electric power system.
The proposed rule includes forms of procedures and an interconnection
agreement for small generators. Public comments on the proposed
rule were due on October 3, 2003.
The proposed rule is a giant step toward streamlining the
process of interconnection of distributed energy to the electric
grid. It also leaves many issues unresolved because FERC has
declined to participate in precertifying facilities and dispute
resolution. In addition, the FERC interconnection rule for
small generators will not apply to all distributed energy
projects but only to projects that interconnect with FERC
jurisdictional transmission facilities. Regardless of the
content of the final rule, FERC has directed much-needed attention
to the problems of small-generator interconnection.
State public utility commissions are also proposing rules
for interconnection of small generators. For example, the
Michigan Public Service Commission issued an interconnection
rule in July 2003 for generating facilities as small as 30
kW connecting to utility distribution systems that are not
subject to FERC jurisdiction. The rule ordered Michigan utilities
to file rules meeting certain specified criteria. The criteria
specify a maximum fee for utility engineering studies. The
Michigan rule also requires utilities to complete the processing
of an interconnection application within 18 weeks after the
application is complete, with a deadline of only two weeks
for facilities no larger than 30 kW. In December 2000, the
California Public Utilities Commission issued a rule containing
requirements for utility interconnection with distributed
energy. The Illinois Commerce Commission is expected to initiate
a rulemaking on interconnection rules for nonutility generation
before the end of 2003.
Interconnection rules require a balancing act. Utility safety
and reliability concerns must be balanced against unduly high
costs and long delays that will discourage distributed energy.
Objective interconnection rules that an important step, as
is implementation of an objective, prompt, and cost-effective
process for resolving disputes between developers of distributed
energy and owners of the transmission or distribution systems
that interconnect with distributed generation. It is too soon
to tell how effective the final FERC small-generator interconnection
rule will be. At the very least, the proposed rule raises
important issues and provides a jumping-off point for rules
that will be adopted at the state level.
FREDDIE L. GREENBERG is principal at Freddi
L. Greenberg Attorney at Law in Chicago, IL.
DE - Nov/Dec 2003
|