|
|
DG provides one-third of this
30 North LaSalle, Chicago, building's electrical requirements. |
| |
 |
Chicago, ILbased Equity Office is the nation's largest
owner and manager of office buildings with more than 721 properties
and 124.4 million ft.2 of office space in 19 states. It therefore
was no small decision when the company committed to a program
of distributed generation (DG). Through its wholly owned subsidiary,
On-site Energy Providers LLP, Equity Office currently has
12 buildings with onsite power plants installed or in progress
and another eight buildings targeted. The company's eventual
goal is as many as 100 DG systems nationwide.
"Economics is the driving force," says Frank Frankini,
On-site Energy Providers senior vice president. "I've
thought about this since the late 1990s when energy deregulation
in the electric markets took off. With regulated monopolies,
onsite generation would have been extremely difficult if not
next to impossible."
Frankini says Equity Office sees DG as a way to improve business
economics, make facility management more efficient, and provide
better reliability to building tenants. All but two of Equity
Office's systems are grid-parallel cogeneration systems. Electrical
power is generated on-site using natural-gasfired reciprocating
engines connected to electrical generators. Thermal energy
accumulated during power generation (waste heat) is recovered
to run the building's heating and cooling systems (via a heat
recovery steam generator or an absorption chiller). The Equity
Office onsite plants are designed to meet a portion of the
building's base load, thus reducing the amount of power purchased
from a utility while at the same time reducing the thermal
load. "We either buy the power for our buildings or we
produce it ourselves," says Frankini. "This has
allowed us to change our load profile and to purchase what
power we do from the utility at a lower price."
Decision-Making Drivers
On-site Energy Providers Vice President of Energy Operations
Tom Smith lists 10 criteria the company applies when evaluating
potential DG projects. "Like anything else, this has
got to make economic sense," says Smith. "What we're
looking at is the difference between what we would displace
in terms of power costs [and] what it will cost to run the
system." Smith admits calculating the right mix isn't
always as straightforward as it might seem. "We're dealing
with commodities. Our biggest expense is the natural gasand
gas prices have been fluctuating. Our biggest income line
is electricity, which is subject to regional forces. What
we're looking for is a margin we feel will be there over the
life of the project." So far Equity Office has identified
six markets where onsite generation makes sense: Boston, Chicago,
Los Angeles, San Francisco, San Diego, and New York City.
The second consideration is fuel. If natural gas isn't available
at the site, this effectively nixes the project. (Barry Kreuzer,
regional sales manager for Cummins Power Generation Energy
Solutions Group in Minneapolis, MN, which has worked with
Equity Office in Chicago, estimates that assuming a Cummins
engine is running 8,000 hours a year, 65% of a project's cost
will be fuel.) The third requirement is a location for the
equipment, typically in a basement or on a roof or perhaps
containerized in a parking garage. Next comes the challenge
of removing the exhaust generated by the engines. If the local
utility is cooperative, all the better since the goal in most
installations is to run the DG plant in parallel with conventional
utility power. Local permitting requirements regarding noise,
aesthetics, and exhaust emissions must also be considered.
Finally, it sweetens the pot and might even make or break
the project if state or local incentives are available to
help defray capital costs.
So far, says Smith, Equity Office has not developed a standard
approach that can be applied across projects. It has handled
some installations itself; others have been accomplished in
concert with outside consultants. Frankini sums up the process:
"You have to know exactly what you consume. Then you
can look at the effect of the various different technologies
and systems on that consumption, then do a detailed engineering
and economic analysis to see what difference onsite generation
can make to your bottom line."
The Big Three
Chach Curtis, vice president of onsite generation for Northern
Power Systems Inc. (in Waitsfield, VT, and San Francisco,
CA), which has worked with Equity Office on DG design and
installation, offers a quick shorthand for assessing whether
installing onsite power is likely to benefit an organization.
The first question, says Curtis, is whether the system will
generate enough savings for the return on investment to meet
an organization's internal requirements. "Most of these
companies have investment benchmarks," says Curtis. "We
want to be able to clear them." The next question is
how much reliability is enough. For some operations, a temporary
five-minute outage can be managed; for others, seconds can
be critical. Third, how important are environmental considerations?
Because of the combined efficiencies of cogeneration systems
in creating energy from electricity and waste heat, there's
a substantial increase in efficiency and a corresponding decrease
in the amount of greenhouse gas produced per unit of power,
which for some companies can be an important decision driver.
Curtis recommends two out of these three conditions be satisfied;
otherwise a DG system might not be worth the investment.
Next Up: Project Engineering
Once the project is given the go-ahead, the engineering begins.
First up is a load profile for the facility, which requires
knowing the electricity demand for each 24-hour period for
a timeframe of two to three years. Utilities supply this information
in 1520 minutes increments, but the data must be analyzed
to determine base and peak usage, an exercise that is critical
to defining the size of generators needed to power the system.
"The economics of onsite generation work best when you
run the generator as much as you can," says Curtis. "You
don't want to size for peak periods because you'll be buying
equipment you don't need. The more you keep your engines running
at close to their rated capacity, the more efficiently you're
going to burn fuel and the more kilowatt hours you're going
to produce for the same amount of fuel burned. To the extent
you size a system to meet the base load, your engines are
going to run more efficiently."
 |
| Cummins 1,100-kW engine generator
set installed at 30 North LaSalle |
At Cummins, Kruezer agrees. "My caution to the customer
is to make sure whoever is doing the load analysis doesn't
oversize the equipment. Not only will this increase your payback
time, but you're going to increase your life cycle costs.
You don't want a piece of equipment running at a 70 to 80%
load. You want it to run 90 to 96%ideally 100%."
As with most organizations using distributed generation,
Smith says Equity Office has elected to stay connected and
run in parallel with the existing utility's grid, which means
tying the building's onsite system into the bus that receives
the utility's power and routes it throughout the building.
Benefits include splitting the electrical load, with the DG
system picking up the more consistent base load and leaving
the utility to pick up the peak, and being able to shut down
for maintenance. So far Equity Office's systems have generally
been designed to handle up to 3540% of building power,
which Curtis says is typical. "The base load in most
office buildings is about a quarter of the peak load. If you
stay connected to the grid, you can have a 1-megawatt-size
generator and still be able to handle a 4-megawatt peak load.
But if you fully disconnect from the utility, you'd have to
resize that generator to 4 megawatts, which means you'll be
running the equipment under capacity much of the time. There's
the additional consideration that when you go down for maintenance,
the utility is there to pick up the full load."

Since it's not meant to generate all of a building's power,
the DG system is typically configured to disconnect from the
grid in the event of a power failure, although with a little
extra work it can be designed to sort among loads and serve
only those that are critical. At one of its two Chicago office
buildings, for example, Equity Office provides full backup
for one tenant's data center. Because the arrangement is exclusive,
the tenant picks up the full cost of the system when it's
running in this mode. "This kind of system architecture,
which relies on digital switches, costs more to make seamless,"
says Curtis, "but it's getting a lot more attention after
the recent blackout on the East Coast. Running parallel with
the utility is a way to provide enhanced reliability for your
tenants over and above the existing grid while at the same
time maximizing your operation. Another nice thing about having
your onsite generator running in parallel with the grid is
that it's already up and running if an outage happens."
Running in parallel requires an interconnect that, as Curtis
points out, is subject to the requirements of the individual
utility. In certain sections of New York, Con Edison calls
for induction generators that require excitation current from
the grid. This type of interconnection will make it more difficult
for Equity Office to provide backup power to tenants at its
Avenue of the Americas building if the grid goes out. And
although it might be true that utilities might not seem supportive
of onsite power and are particularly protective of their downtown
grids, Curtis suggests there are reasons.
"The utilities look at onsite generation as a potential
safety risk for the grid," says Curtis, "particularly
in a downtown network like the one that serves Equity Office's
One Market Plaza building. Most states have issued interconnection
standards, but there's a lot of room for interpretation and
this can cause problems. At the simplest level, the utility
is trying to prevent the onsite generating unit from backfeeding
into its grid, which endangers both the system itself and
anyone who might be working on it when it's down.
"Fortunately the technology is such that these concerns
are easily addressed if you take the time and know what you're
doing. We were able, for example, to mate One Market Plaza's
large-scale onsite generating system to Pacific Gas and Electric's
downtown grid, when the utility had never before allowed an
onsite generator to run parallel within the downtown area.
The critical factor was working carefully with network-protection
engineers to demonstrate that our control system was robust
enough to prevent any of the possible scenarios that could
create safety or reliability issues."
Capturing What Would Otherwise Be
Lost
A sound economic and engineering plan should also include
how facility managers can take advantage of the cogenerational
capacity of DG systems. "Most people think electricity,"
says Kreuzer, "but you can receive two forms of energy
from that generator set. At one of the Equity Office buildings
in Chicago, we fed the waste heat into a steam boiler and
reduced the demand on those gas-fired units."
Curtis thinks taking advantage of waste heat is critical
for the economics of a project. "You increase the efficiency
of the system dramatically and make it pay for itself that
much quicker. In fact, utilizing waste heat can often make
the difference between whether a project is economically viable
or not. In a project like Equity Office's buildings in La
Jolla, California, where there's a large air-conditioning
demand, you can use most or all of your waste heat to drive
absorption chillers that create chilled water for your air-conditioning
system. At the Avenue of Americas building in New York, you
can use the waste heat to heat the building in winter and
cool it in the summer."
But at One Market Plaza in San Francisco, where it is neither
as hot as La Jolla nor as cold as New York, the situation
is not as clear-cut. Fortunately California (through the Self-Generating
Incentive Program of the California Public Utility Commission)
is one of a number of statesincluding New York (through
the New York State Energy Research and Development Authority),
New Jersey, Connecticut, Massachusetts, and Rhode Islandthat
offer incentives for DG installations. At One Market Plaza,
Curtis explains that incentives pay 30% of the capital costs
if the system meets a combined electrical and thermal efficiency
of 62% (meaning the system converts 62% of the fuel consumed
into usable electricity or thermal energy).
The Northern Power Systems engineering that brought One Market
Plaza to the required benchmark operates as follows: "The
engine itself [runs] at approximately 32% efficiency,"
explains Curtis, "but making up the other 30% through
recovering the heat of the exhaust and converting it into
usable thermal energy was going to be difficult. We knew,
however, that One Market Plaza project costs were high, and
if we demonstrated that we could get an incentive, it would
go a long way toward convincing Equity Office's investment
committee that they should invest in this kind of project.
So we designed a system that took heat from both the exhaust
and the engine itself through a cooling water loop that circulated
around the engine block. Then we ran the heat from both these
sources through a heat recovery steam generator and then ran
the resulting steam into a steam loop that runs through the
building. One of the keys was being able to tie into the steam
loop at a key connection pointthe more connection points
and the farther you have to run the recovered heat, the more
it gets dissipated, which lowers your efficiency."
 |
 |
| One Market Plaza building in
San Francisco (top) and the three engines located
in its basement area (bottom) |
Location,
Location, Location
"One of the factors that make this work interesting,"
says Curtis, "is that no two buildings are the same."
This means where to locate an onsite power system varies from
one location to another. Some of the units go on the roof,
if the roof is designed to hold 200,000 lb. or moreand
isn't already full of other equipment. Putting a system on
a roof might also be prohibitive, given costs associated with
getting equipment to the site, which in a place like San Francisco's
financial district can be considerable. There is also the
option of taking two or three spaces in a parking garage and
installing a container with sound attenuators or generator
mufflers and exhaust and otherwise baffling the equipment.
Curtis recommends the basement as the best option, but this
requires the installation of dampening equipment so the generators
don't vibrate the building. At One Market Plaza the generator
sets were installed in a vacant part of the basement that
formerly housed backup generators.
As Curtis points out, some of these logistics challenges
will be resolved as more buildings are constructed with DG
systems in mind, which will eliminate the need for retrofitting.
Until then, both locating the onsite plant and routing the
exhaust out of the building are factors that have to be addressed
when planning for onsite power. "These large, reciprocating-based
power plants in the size range that Equity Office needs are
engineering-intensive," says Kreuzer, "and we have
to deal with the building's existing infrastructure and physical
operating scheme. The generator set we installed in one of
Equity Office's Chicago buildings, for example, is in the
second or third subbasement of a skyscraper. There's a lot
of design work that went into that."
Other engineering challenges include meeting local emissions
standardslargely a measure of seeing that catalytic
converters are sized properly to meet local standardsand
securing the necessary permits, which means making sure the
unit meets local noise and environmental requirements. Smith
says typical time to get a system up and running from conceptual
design to operation is from eight to 12 months. He estimates
that by the time all installations are complete, the cost
of DG in 12 buildings Equity Office originally targeted will
run $15 million with incentives.
 |
| Viewing the operational status
of the 1,100-kW cogeneration system at 30 North LaSalle |
Responsibility for Equity Office's onsite facilities falls
with current building management. Major maintenance typically
is contracted out to local vendors. "We use our own existing
engineering staff within the buildings to operate the units,"
says Smith. "For the engine generator sets we contract
with the manufacturer. The rest of the equipment we maintain
either with our engineers or through third-party contracts.
We're tapping into our building-management experience. We've
put in chillers and boilers and other electrical equipment
and have good relationships with suppliers." Kreuzer
paints a picture of what maintenance on a typical Cummins
generator set is likely to look like. "In California,
for example, most of our applications are running 8,000 hours
a year as opposed to 3,400 hours in Chicago. That means that
after seven and a half years we would have to do a major rebuild.
Typically we're looking at doing at least two rebuilds, which
takes us to 180,000 hours, which is a pretty good life cycle
on a generator set that gives above 38% electrical efficiency."
Regarding what they would do differently, now that they have
some DG experience under their belts, both Smith and Frankini
say there have been few surprises. "The technology has
been around for a long time," Smith points out, "and
both Frank and I come out of the power industry. You have
to remember the entire system is designed for economics, and
for this you have to look at the big picture. Since 1970,
the electrical load in downtown Chicago has doubled. The more
buildings that install distributed energy in these constrained
downtown areas the easier it's going to be on utilitiesand
for managers and tenants who occupy these buildings."
Journalist PENELOPE GRENOBLE O'MALLEY
is a frequent contributor to Forester Communications publications.
DE - Nov/Dec 2003
|